P1 Archetecture and Industry

.docx

School

University of Nebraska, Omaha *

*We aren’t endorsed by this school

Course

1030

Subject

Civil Engineering

Date

Apr 3, 2024

Type

docx

Pages

2

Uploaded by DeanIron10559 on coursehero.com

Durham School of Architectural Engineering & Construction, University of Nebraska AREN 2030 – Design Studio II P1: Architecture & Industry ASSIGNMENT Select the best answer. 1. Who is responsible for verifying that recessed downlights do not interfere with the ductwork shown on the plans ? a. Architect b. Electrical engineer c. Lighting designer d. Mechanical engineer 2. Which of the following are likely to occur if the drawings and specifications are not thoroughly coordinated? (Choose four) a. a. A decrease of the actual cost from the estimated cost because the contractor bid on a less expensive material shown on the drawings, although the same material was called out as a more expensive type in the specifications. b. A lawsuit c. The need for a change order during construction, to account for modifications required to correct discrepancies in the two documents d. A delay in construction e. An increase in cost because the contractor bid the least expensive choice between two conflicting requirements when the client wanted the more expensive option f. The architect may be held financially responsible for the omission. 3. Which of the following statements about specifications are true? (choose two) a. a. Both narrow scope and broad scope sections can be used the same project manual. b. Drawings are more binding than specifications if there is a conflict . c. Specifications show quality, drawings show quantity. d. Proprietary specifications encourage competitive bids. e. Specifications should not be open to interpretation if they are the “base bid with alternates” type f. Proprietary specifications are the most difficult for an architect to write. 4. During the final stages of contract document development, the electrical engineer discovers that mechanical ductwork is shown on the mechanical engineering drawings in a position that interferes with electrical conduit. The person responsible for resolving the conflict is: a. a. Electrical engineer b. Mechanical engineer c. Contractor d. Architect 5. Which of the following is the contractor solely responsible for? a. I. Field reports to the owner II. Field tests III. Scaffolding IV. Reviewing claims of subcontractors V. Reviewing shop drawings i. A. II and III only B. IV and V only C. I, II, and III only D. II, III, and IV only 6. The architects drawings released for bidding indicate an area of exterior concrete paving with an indeterminate limit because the owner has not made a final decision concerning the amount of paved area wanted. In order to fairly compare bid prices for the paving, the architect may request on the bid form that the contractors include: a. a. Individual quotes b. Unit prices c. Fixed costs d. contingencies 7. During a site visit, the architect notes that the contractor is using unapproved materials that were not originally specified. Before work can be stopped under the provisions of the AIA document A201 what must occur? a. a. The contractor must show cause why the unapproved materials are being used. b. The owner must issue a written order to the contractor to stop work. c. The architect must give written notice of intent to stop the work and wait seven days. d. The architect, with the approval of the owner, must issue a stop work order.
8. During construction, the architect suspects that an incorrect type of plumbing piping has been installed. However, the contractor has covered the work with a partition because the architect did not request in advance to examine it. The architect now requests that the contractor tear out a portion of the partition in order to facilitate inspection. Upon review, the plumbing is found to be incorrect. The party responsible for the cost of uncovering the work is the: a. a. Architect b. Owner c. Contractor d. Plumbing subcontractor 9. Which of the following is probably of LEAST concern to a subcontractor? a. a. The number of times equipment must be mobilized b. The types of tools needed to build a project c. Workers’ skills level needed to complete the work d. Other trades that will be working on the same part of the construction at the same time 10. During a periodic visit to the site, the architect notices what appears to be an undersized variable air volume box being installed. What should the architect do? a. a. Tell the mechanical engineer to look at the situation during the next site visit by the engineer. Note the observation on a field report b. Find the contractor and stop work on the installation until the size of the unit can be verified by the mechanical engineer and compare to the contract documents. c. Notify the owner in writing that the work is not proceeding according the to the contract documents and advise him to stop the work until the architect can arrange a meeting with the mechanical engineer to resolve the situation d. Notify the contractor that the equipment may be undersized, and have the contractor check on it. Concurrently ask the mechanical engineer to verify the size of the unit against the specifications and report to the architect. 11. Contract documents form the basis of the legal relationship between the a. a. Owner and architect b. Contractor and subcontractor c. Architect and contractor d. Owner and contractor 12. Which of the following is NOT part of the contract documents? a. a. An addendum b. Bidding documents c. General conditions of the contract for construction d. Change orders 13. An architect suspects that blocking has been installed in the wrong location and asks that a portion of the work be uncovered. When the drywall is removed, the blocking is found to be in the correct location. Who is responsible for paying for the removal and replacement of the portion of the wall? a. a. The architect b . The owner c. The contractor d. The architect and the owner should split the cost 14. Which of the following architectural services are NOT typically within the scope of an architect’s basic services? a. a. Programming b. Schematic design c. Design development d. Construction documents 15. The Contractor is frustrated with all of the changes the Owner is making during construction. What actions is the contractor permitted to take without significant ramifications? a. a. The Contractor may walk off the job b. The Contractor can request the Architect to issue change orders for additional time and compensation c. The Contractor can issue change orders for additional time and compensation d. The Contractor may hire another contractor to complete the job
Your preview ends here
Eager to read complete document? Join bartleby learn and gain access to the full version
  • Access to all documents
  • Unlimited textbook solutions
  • 24/7 expert homework help