2. If EcoScape uses a normal costing system and overhead is applied on the basis of direct labor ho What is the overhead rate? Round your answer to the nearest cent. per direct labor hour What is the average actual wage rate? per direct labor hour What is the cost of an installation that takes $3,650 of direct materials and 20 direct labor hours?

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter6: Activity-based, Variable, And Absorption Costing
Section: Chapter Questions
Problem 11EA: Potterii sells its products to large box stores and recently added a retail line of products to sell...
icon
Related questions
Question
1. Should EcoScape use process costing or job-order costing?
Job-order costing
2. If EcoScape uses a normal costing system and overhead is applied on the basis of direct labor hours,
What is the overhead rate? Round your answer to the nearest cent.
per direct labor hour
What is the average actual wage rate?
per direct labor hour
What is the cost of an installation that takes $3,650 of direct materials and 20 direct labor hours?
Transcribed Image Text:1. Should EcoScape use process costing or job-order costing? Job-order costing 2. If EcoScape uses a normal costing system and overhead is applied on the basis of direct labor hours, What is the overhead rate? Round your answer to the nearest cent. per direct labor hour What is the average actual wage rate? per direct labor hour What is the cost of an installation that takes $3,650 of direct materials and 20 direct labor hours?
Characteristics of Production Process, Cost Measurement
Vince Melders, of EcoScape Company, designs and installs custom lawn and garden irrigation systems for homes and businesses throughout the state. Each job is different,
requiring different materials and labor for installing the systems. EcoScape estimated the following for the year:
Number of direct labor hours
6,530
Direct labor cost
$65,300
Overhead cost
$50,281
During the year, the following actual amounts were experienced:
Number of direct labor hours
6,145
Direct labor incurred
$67,595
Overhead incurred
$52,152.62
Transcribed Image Text:Characteristics of Production Process, Cost Measurement Vince Melders, of EcoScape Company, designs and installs custom lawn and garden irrigation systems for homes and businesses throughout the state. Each job is different, requiring different materials and labor for installing the systems. EcoScape estimated the following for the year: Number of direct labor hours 6,530 Direct labor cost $65,300 Overhead cost $50,281 During the year, the following actual amounts were experienced: Number of direct labor hours 6,145 Direct labor incurred $67,595 Overhead incurred $52,152.62
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College