5. Given the following cost expenditures (see Table P6.3) for a small bridge job to include direct and indirect charges (but not bank interest): A. Calculate the peak financial requirement. B. Sketch a diagram of the overdraft profile. Assumptions: • The markup for this project is 8%. • Finance charge is 1% per month.

Managerial Economics: Applications, Strategies and Tactics (MindTap Course List)
14th Edition
ISBN:9781305506381
Author:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Chapter17: Long-term Investment Analysis
Section: Chapter Questions
Problem 5E
icon
Related questions
Question
5. Given the following cost expenditures (see Table P6.3) for a small bridge
job to include direct and indirect charges (but not bank interest):
A. Calculate the peak financial requirement.
B. Sketch a diagram of the overdraft profile.
Assumptions:
• The markup for this project is 8%.
Finance charge is 1% per month.
REVIEW QUESTIONS AND EXERCISES
157
TABLE P6.2 Project Bar Chart
Month
Activity
1
3.
4
1. Survey
$2,000
2. Mobilization
$1,200
3. Trench
$3,000
$6,000
4. Lay pipe
$3,000
5. Concrete
$500 $500
6. Backfill
$500
7. Move out
$500
8. Prepare valves
$1,000
9. Install valves
S1,000
10. Test
$1,500
Retainage is 6% throughout project.
Payments are billed at the end of the month, and are received one month
later.
TABLE P6.3 Monthly Costs for Bridge Job
Month
1
2
3
Monthly cost*
29,000
48,900
16,400
* Direct cost + indirect cost
Transcribed Image Text:5. Given the following cost expenditures (see Table P6.3) for a small bridge job to include direct and indirect charges (but not bank interest): A. Calculate the peak financial requirement. B. Sketch a diagram of the overdraft profile. Assumptions: • The markup for this project is 8%. Finance charge is 1% per month. REVIEW QUESTIONS AND EXERCISES 157 TABLE P6.2 Project Bar Chart Month Activity 1 3. 4 1. Survey $2,000 2. Mobilization $1,200 3. Trench $3,000 $6,000 4. Lay pipe $3,000 5. Concrete $500 $500 6. Backfill $500 7. Move out $500 8. Prepare valves $1,000 9. Install valves S1,000 10. Test $1,500 Retainage is 6% throughout project. Payments are billed at the end of the month, and are received one month later. TABLE P6.3 Monthly Costs for Bridge Job Month 1 2 3 Monthly cost* 29,000 48,900 16,400 * Direct cost + indirect cost
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Investments
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, economics and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Managerial Economics: Applications, Strategies an…
Managerial Economics: Applications, Strategies an…
Economics
ISBN:
9781305506381
Author:
James R. McGuigan, R. Charles Moyer, Frederick H.deB. Harris
Publisher:
Cengage Learning