8. QUESTION EIGHT Choose the correct statement below A) The critical path consumes the maximum time B) The activities connecting the events having zero slack lie on the critical path. C) The difference of the latest occurrence time and earliest expected time is called slack. D) All above 9. QUESTION NINE If the optimistic time, most likely time and pessimistic time for an activity A are 40,60 and 80 hours respectively and for activity B are 50,55 and 90 hours respectively, then. A) Expected time of activity A is greater than expected time for activity B B) Expected time of activity B is greater than the expected time of activity A C) Expected time of both activities A and B are the same D) None of the above. 10. QUESTION TEN Indicate the correct statement from the following; A) Optimistic time estimates refer to activities B) Pessimistic time estimates refer to activities C) Most likely time estimates refer to activities D) All above 11. QUESTION ELEVEN In resources levelling A) Total duration of project is reduced B) Total duration of the project is increased C) Uniform demand of resources is achieved D) Cost of project is controlled
8. QUESTION EIGHT Choose the correct statement below A) The critical path consumes the maximum time B) The activities connecting the events having zero slack lie on the critical path. C) The difference of the latest occurrence time and earliest expected time is called slack. D) All above 9. QUESTION NINE If the optimistic time, most likely time and pessimistic time for an activity A are 40,60 and 80 hours respectively and for activity B are 50,55 and 90 hours respectively, then. A) Expected time of activity A is greater than expected time for activity B B) Expected time of activity B is greater than the expected time of activity A C) Expected time of both activities A and B are the same D) None of the above. 10. QUESTION TEN Indicate the correct statement from the following; A) Optimistic time estimates refer to activities B) Pessimistic time estimates refer to activities C) Most likely time estimates refer to activities D) All above 11. QUESTION ELEVEN In resources levelling A) Total duration of project is reduced B) Total duration of the project is increased C) Uniform demand of resources is achieved D) Cost of project is controlled
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
Related questions
Question
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.Recommended textbooks for you
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning