A contractor has agreed to build 10 dog houses in 20 days at a price of $800 per unit. 10 days later, the contractor has finished 6 dog houses with an actual total cost of $5,200. What is the cost variance CV (CV = BCWP-ACWP)? $800 C$400 $-1,200 $600

Marketing
20th Edition
ISBN:9780357033791
Author:Pride, William M
Publisher:Pride, William M
Chapter19: Pricing Concepts
Section: Chapter Questions
Problem 6DRQ
icon
Related questions
Question
A contractor has agreed to build 10 dog houses in 20 days at a price of $800 per
unit. 10 days later, the contractor has finished 6 dog houses with an actual total
cost of $5,200. What is the cost variance CV (CV = BCWP-ACWP)?
$800
C$400
$-1,200
$600
Transcribed Image Text:A contractor has agreed to build 10 dog houses in 20 days at a price of $800 per unit. 10 days later, the contractor has finished 6 dog houses with an actual total cost of $5,200. What is the cost variance CV (CV = BCWP-ACWP)? $800 C$400 $-1,200 $600
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Marketing
Marketing
Marketing
ISBN:
9780357033791
Author:
Pride, William M
Publisher:
South Western Educational Publishing