a) Identify each path and path duration b) Identifying due time of the critical path c) Compute for te, Path total, v path v pth of the critical
Q: Chapter Exercises A project has been defined to contain the following list of activities along with…
A: b.
Q: 4. Schedules and activities of a project are shown below. Answer the questions. Activity…
A: A) The CPM chart is as follows: The critical path is: A-D-E-H-I-L
Q: 2) Draw the network corresponding to the following information. Also, complete the table, identify…
A: Critical Path : B----D----G----H Critical Path Duration : 30
Q: Consider the following information for a project to add a drive-through window at Crestview Bank.a.…
A:
Q: A. Construct a network for the project outlined below and determine the critical path time B.…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: ACTIVITY PREDECESSORS DURATION (DAYS) A 3 B A 4 A D B 5 1 F D,E F,G 4 3 You are required to a) Draw…
A:
Q: 4. Calculate the late finishing time (backwards calculations) 5. Calculate the slack time of the…
A: Formula:
Q: a. Draw a project network. b. Identify the critical path. e Develop the activity schedule for the…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: Consider the following information for a project to add a drive-through window at Crestview Bank. a.…
A: b. The critical path is B-E-G-H. c. Slack for the activities A and D are 8 each.
Q: a. Construct an arrow diagram for this problem b. Determine the critical path and compute the…
A: ANSWER IS AS BELOW:
Q: Q2. Consider the following data summarizing the details of a project involving 12 activities.…
A:
Q: A project has been defined to contain the following activities, along with their time estimates for…
A: The Critical path diagram of the given activities as follows -
Q: 5. Calculate the slack time of the non-critical path activities 6. Identify the critical path…
A: Formula:
Q: (1) O Construct a network diagram with activity on arrow method; (1) Estimate the expected project…
A:
Q: a. Draw a project network b. Identify the critical path c. Develop the activity schedule for the…
A: A project schedule network diagram shows the tasks that are to be performed in the defined sequence.…
Q: A project has been defined to contain the following list of activities along with their required…
A: AS PER THE BARTLEY POLICY ANSWER FIRST FOUR SUB-PARTS OF THE QUESTION. PLEASE POST OTHERQUESTIONS…
Q: REQUIRED: 1. Draw an Activity-on-Node network diagram for the project 2. Compute the Early Start…
A:
Q: 1. Draw a project network given the following information. 2. Complete the forward and backward pass…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Draw the network of the following Table and determine critical path using CPM| preceded by Duration…
A: Given Information:
Q: Identify critical path and total time (i.c. number of hours) required to complete the path). Find…
A: A network diagram representing a project in visual model using arrows and nodes. A critical path is…
Q: A Project has been defined to contain the following list of activities along with their required…
A: a) The network diagram based on the given information is as follows: Note: EF = Early Finish Time…
Q: H.W(1):- Draw Gantt chart for the following project and determine the duration of the project…
A: A Gantt chart is a type of bar chart. It shows the schedule of a project. It was invented by Henry…
Q: A project for improving a billing process has the following precedence relationships and activity…
A: A network diagram is used a graphical representation of all the activities and the work sequence,…
Q: 1. Determine the amount of slack in each of a project's activities (presented below), and identify…
A: We’ll answer the first question since the exact one wasn’t specified. Please submit a new question…
Q: 6. A Project network is shown below. Use forward and backward pass to determine th critical path and…
A: PERT is very useful techniques which are common among organizations to reduce cost and to represent…
Q: 1.2 A planned project contains the activities shown in the table below, along with their reqi…
A: A Gantt chart, which is widely used in project management, is one of the most popular and practical…
Q: QI/ The following table shows the activities of a construction project, sequences and estimated…
A:
Q: Draw the PERT network and the Gantt chart. Find the critical path What is the length of the critical…
A: THE ANSWER IS AS BELOW:
Q: 1. of all the paths through a network , the critical path has the a. Maximum actual time b.…
A: Project network is the graphical representation that shows the project activities as well as their…
Q: Example - Draw Activity on Node Diagram Activity Predecessor Duration A B A 3 B E F G C,F 5 H G 4 G…
A: Activity Immediate Predecessors Duration A - 5 B A 3 C B 4 D - 5 E D 7 F E 2 G C,F 5…
Q: Construct a CPM network based on activity on node method with the details given below and find the…
A: Given information, Activity Immediate Predecessor Duration A 1 B A 4 C A 2 D A 2 E…
Q: Ex7: (H.W) Draw the network of the following Table and determine critical path using CPM Act.…
A: Given Information, Activity Preceded By Duration A 3 B A 5 C A 4 D A 6 E B 4 F…
Q: Schedule the lowing project by using network , EF, LS, LF, TF, FF). Also show the critical path.…
A: Given that: Activity Duration A 2 B 7 C 10 D 4 E 6 F 5 G 8 H 9 I 12 J 5 K…
Q: 5. Construct an activity-on-arrow precedence diagram for each of the following cases. Note that each…
A: The project network is the visual representation of the project activities and their durations to…
Q: 2. A network consists of the activities in the following list. Times are given in days. Activity…
A: Given data is
Q: The activities related to a project with their immediate predecessors are given as follows: Activity…
A: Given data is
Q: Construction of a building is based on the followingCPM network:a. Draw the network for this project…
A: "Since you have posted a question with multiple sub-parts, we will solve first three sub-parts for…
Q: 1. A project has been defined to contain the following list of activities along with their required…
A: Note: You have posted multiple questions with multiple subparts, we can solve only one question per…
Q: For the small project with the relationships shown below. Activity IPA's Duration (Day) A В 7 C 4…
A: Given Information:
Q: Instructions: 1. Make the project network diagram 2. Find the project duration 3. Solve for 4.…
A: For each non-critical activity, the total float, free float, and independent float calculations are…
Q: Instructions: 1. Make the project network diagram 2. Find the project duration 3. Solve for…
A: Note: - Since we can answer only up to three subparts we will answer only the first three subparts…
Q: 8) Assume you have a project with ten activities labeled A-J. Derive the earliest completion time…
A:
Q: Immediate Activity Predecessor Time (days) 8 в 20 33 18 D E 20 F B B.C 10 H D EF G, H, I 4 (End) a)…
A: A network diagram is a visual representation of a project which helps to identify the project…
Q: A D A A B,C D H D,E F H,G You are required to a) Draw the network diagram b) Calculate ES, EF, LS,…
A: The answer is as below:
Q: Activity Immediate Predecessor Time A 5 B A 8. B D A 8 9. F C 2 G D, E H F 7 G 4 H, I 3
A: Given activities-
Q: Q2. Consider the following data summarizing the details of a project involving 12 activities.…
A:
Q: Determine a) The slack available of every activity. b) The critical path c) The duration of the…
A: Project network is the diagram that shows the project tasks or activities and their duration to…
Q: Draw the project network diagram. 1. What is the total time required to complete the project if no…
A: Network analysis (NA) could be a set of integrated techniques to depict relations among actors and…
Q: A project has been defined to contain the following list of activities along with their required…
A: D. Even if there is change in activity 6 to take 6 weeks instead of 1 week there is no change in the…
Q: draw the precedence network diagram, project duration and critical path for this project
A: THE ANSWER IS AS BELOW:
conduct pest analysis for the data by
Step by step
Solved in 2 steps with 3 images
- Period (t) Enrollment (1000s) 1 6.5 2 8.1 3 8.4 4 10.2 5 12.5 6 13.3 7 13.7 8 17.2 9 18.1 Develop a linear regression with a dependent variable of “Enrollment (1000s). A.What is the value of R square? (Make sure two decimal places.) B.What is the value of intercept? (Make sure two decimal places.) C.What is the coefficient value of Period (t)? (Make sure two decimal places.) D.Is the coefficient of Period (t) significant? (Yes:1, No: 0) E.What is the forecast for year 10?php?attempt=104149&cmid%330865 aline Services v OS Ticket system My Dispense Academic Calendar N My courses 3) v Q b) Calculate the weighted moving average for periods 7 through 10 using weights of 0.6, 0.3, and 0.1. n Lo S : Cha Weighted moving Period Actual average 1 64 2 84 3 91 4 97 115 6. 135 7. 137 8. 144 6. 153 10 171 beriods 7 through 10. Use 5.Percentage Service Provided toDepartment Cost S1 S2 P1 P2Service 1 (S1) $ 112,000 0% 40% 40% 20%Service 2 (S2) 44,000 20 0 40 40Production 1 (P1) 345,000Production 2 (P2) 216,000Total $ 717,000Brief Exercises 7-15 and 7-16 require the following information:7-15 What percentage of S1’s costs is allocated to P1 and to P2 under the direct method?7-16 What percentage of S2’s costs is allocated to P1 and to P2 under the direct method?
- Identify the term being described for each of the following: f. The statistical distribution used to describe path variability.A marketing analyst wants to examine the relationship between sales (in $1,000s) and advertising (in $100s) for firms in the food and beverage Industry and collects monthly data for 25 firms. He estimates the model Sales-o Advertising. The following ANOVA table shows a portion of the regression results. Regression Residual df 1 23 55 78.53 504.02 MS 78.53 21.91 T 3.58ull touch 1:28 PM 49% Expert Q&A Done On January 1, 2010, P Company acquired the net assets of S Company for $1,580,000 cash. The fair value of S Co. identifiable net assets was $1,330,000 on this date. P Company decided to measure goodwill impairment using the present value of future cash flows to estimate the fair value of the reporting unit (S Co.). The information for these subsequent years is as follows: Carrying value of S Co. Identifiable Net Assets $1,160,000 $1,120,000 Fair Value S Co. Identifiable Net Assets Present value of Future Cash Flows $1,400,000 $1,390,000 * Identifiable net assets do not include goodwill. Year $1,190,000 $1,210,000 2011 2012 Choose the correct answer: In year 2011 S Company had: O Excess of fair value over carrying value of $10,000 O Excess of carrying value over fair value of $10,000 O Excess of fair value over carrying value of $20,000 Excess of carrying value over fair value of $20,000 O None of the options is correct
- find mean and sd . Outcome Probability 1 0.2 2 0.5 3 0.2 4 0.1ic 2-Time Series Analysis and F eBook Problem 6-21 (Algorithmic) The Centers for Disease Control and Prevention Office on Smoking and Health (OSH) is the lead federal agency responsible for comprehensive tobacco prevention and control. OSH was established in 1965 to reduce the death and disease caused by tobacco use and exposure to secondhand smoke. One of the many responsibilities of the OSH is to collect data on tobacco use. The following data show the percentage of U.S. adults who were users of tobacco for a recent 11-year period (http://www.cdc.gov/tobacco/data_statistics/tables/trends/cig_smoking/index.htm). Year 1 2 3 4 5 6 7 8 9 10 11 Percentage of Adults Who Smoke 22.9 25 Peremt of Adults Who St 20 15 21.5 20 8 20.8 a. Choose the correct time series plot. (0) 10 20.1 20.1 18.0 18.9 19.4 19,4 20.3 20.3 20.3 19.4 18.8 4 Year (0) $ 10 12 (1) Percent of Adults Who Smoke 25 20 15 10 Year (0) S 10 12 4Construct AON diagram for the following data. АСTIVITY IMMEDIATE PREDECESSORS A B АВЕ E ACD F BDG G EF H DF FG J FHI K HL L GJK M J,K,L N M
- A mortgage loan onginator (MLo) who is also a real estate broker and refers a customer to a settierent services provider owned by their real estate brokerage must identify this relationship to a borrower on whie the following disclosures? A) Initial loan estimate B) Special information booklet C) Third-party service providers D) Affiliated business arrangement 4:15 PMS9. A Co-operative bank QLB grants loansunder the following conditions. -(a) If customer has an account witbank and has no loan outstandingwill be granted.(b) If customer has an account with thebank but some amount is outstandingfrom previous loan, then loan will begranted if special arrangementapproval is obtained.(c) Reject loan applications in all other cases. Draw Decision Tree and Table for the bank . This under System Analysis and Design.QUESTION 1The table below shows the sales figures for a brand of shoe over the last 12 months.Months SalesJanuary 69February 75March 86April 92May 95June 100July 108August 115September 125October 131November 140December 150a. Using the following, forecast the sales for the months up to January the following year:-i. A simple three month moving average. ii. A three period weighted moving average using weights of 1, 2 and 3. Assign thehighest weight to the most recent data. iii. Exponential Smoothing when α= .6 and the forecast for March is 350.iv. Determine which of the three forecasting technique is the most accurate usingMAD. b. The following table shows the number of televisions sold over the last ten years at alocal electronic store.YEAR TV SALES1 1502 3003 4804 6005 6306 6407 7008 8259 90010 980i. Using trend projection, develop a formula to predict sales for years 11 and 12. Youhave to show all working. You will need to develop a table to calculate the slope andthe intercept.…