Activity Duration(days) Construct the network and find critical path. 1-2 1-3 2-4 3-4 3-5 4-9 5-6 5-7 6-8 7-8 8-10 9-10 1 4 1 1 4 1 5 7
Q: CASE NO.4 4. The National Dog Food Corp. wants to mix 5000lb of special dog food. There are two prin...
A: Given data is Cost of x1 = Php 30 Cost of x2 = Php 60 Limitation of x1 = less than or equal to 4000 ...
Q: Instruction: Round to the nearest integer percentage. What is the implied utilization of the bottlen...
A: Implied Utilization = Demand or Workload/Capacity
Q: People are served in a process with two resources. The first resource has a capacity of 1.4 people p...
A: Given, Total capacity of resource = Capacity * Number of workers Additional worker = 3+1 = 4 Total c...
Q: briefly discuss the process on how you can successfully implement the TQM in their business
A: A Small Introduction to TQM TQM (Total Quality Management) TQM is an administration approach that d...
Q: Select one or more: a. A pie chart would be better O b. Change all the bars to gray. c. Sort the bar...
A: The chart represents the inventory level of farm animals, there are five animals, these are horses, ...
Q: You are an Engineering Manager in Company XYZ and the CEO wanted you to choose ONE of the following ...
A: Plans on the building of a bridge are continually expected to type harmony among cost, time, & q...
Q: a. Draw the CPM Network b. What is the critical path c. What will the scheduled (earliest completion...
A: In the question, we have Activity Table data, this table data includes activity ID, Immediate predec...
Q: Which one of the following perils would be covered under the commercial property policy broad form b...
A: Commercial property insurance covers the repair or replacement of building and building property dam...
Q: Find the solutions: 1.0bjectives 2.Decision Variables 3. Certainty 4.. Parameters
A: The question has been asked to determine the number of stand fans and desk fans that manufacturer mu...
Q: QUESTION 2 2.1 Discuss the stages in the development of the procurement function, their characterist...
A: 2.1) Procurement process or function are a series of steps or processes that is essential to obtain ...
Q: Discuss the several types of changes that may suggest a need to revaluate and/or redesign firm's log...
A: A logistics network is an effective logistics network modeling to move goods from their raw state th...
Q: Provide various reasons as to why project costs may exceed the estimate and provide an alternative s...
A: Project costs are the sum amount of all the funds that is necessary to complete a particular project...
Q: A company is considering the relocation of its manufacturing plant and administrative offices from a...
A: Corporate social responsibility is responsibility of the company towards the society . It is a self-...
Q: (d) A company has three factories. Each factory produces three different products (A, Band C). Facto...
A:
Q: World Foods, Inc., imports food products such as meats, cheese, and pastries to the United States fr...
A: We first tabulate the given data in a consolidated form by combining both the tables which are easy ...
Q: (a) Compute the forecast sale using a = 0.20 and a = 0.35 respectively, (b) solve for MAD, SSE, MSE,...
A: Forecasting is the process of estimating the future demand using previous or historic data or inform...
Q: Jenny Company produces two types of pants: long pants and short pants. The cost of making a pair of ...
A:
Q: GulfOil Company (GOC) can buy two types of crude oil: light oil at $49/barrel and heavy oil $45/barr...
A: Part (A): Decision Variable: Suppose-X1= Barrels of light oil to purchaseX2= Barrels of heavy oil ...
Q: Describe what factors you would consider in deciding to relocate and rank them in order of importanc...
A: Regardless of the fact that allowances and reimbursements for overseas assignments are costly, the f...
Q: Research about ABC Analysis of Inventory management and then describe its salient features.
A: ABC Analysis of Inventory management ABC analysis is a strategy for inventory management that assess...
Q: What is Information Search Process (ISP)? Who initiated this method and how does the researchers ben...
A: Management information systems often called MIS systems can be stated as the division or department ...
Q: Think of a specific mode of transportation in the Philippines. In no more than three (3) sentences f...
A: Due to increase industrialization and urbanization over time, the demand for transportation has als...
Q: The availability of a system is affected when the mean time between failures (MTTR) is approaching z...
A: Mean Time Between Failures (MTBF) helps to specifies how long a new system and repaired system wil...
Q: A campus deli serves 300 customers over its busy lunch period from 11:30 am to 1:30 pm. A quick coun...
A: A queuing system refers to the system that has service facility where the customers arrive for servi...
Q: Three jobs are to be scheduled on two machines A and B. Assume that the jobs are processed in the se...
A: Job A B 1 5 4 2 7 7 3 3 5
Q: Give examples of Repetitve Work not a project and explain
A: A project in other words is a prototype with a goal to be achieved for the further growth of the cor...
Q: In a fabric manufacturing factory, the quality control process using control charts from SPC. In an ...
A: Given-
Q: 2. National Scan, Inc., sells radio frequency inventory tags. Monthly sales for a seven-month period...
A: Forecasting is the process of estimating the future demand using the previous or historic data of sa...
Q: Entrepreneurs may use a minimum viable product for a lean startup process. Define this process.with ...
A: A minimum viable product (MVP) is a concept in the lean start up that would focus on the impact of l...
Q: How do you distinguish between research method and research design?
A: Note - Hi! Thank you for the question As per the honour code, We’ll answer the first question since ...
Q: Give a detailed account of the project report writing highlighting the importance of the various re...
A: Reporting in project management is to have a higher overview that provides the important data relate...
Q: In project manangement what is a scope baseline?
A: Before defining the project scope baseline one needs to understand the project scope. Project scope ...
Q: Why is the Work breakdown Structure not practical for small organizations?
A: A work breakdown structure is an essential project management tool which is used in the following - ...
Q: What are the primary areas of concern for risk management, and how would you define them?
A: Risk management: The process of identifying, analysing and controlling of hazards/risks for the orga...
Q: Valencia Products makes automobile radar detectors and assembles two models: LaserStop and SpeedBust...
A: Objective Functions and Constraints: Based on the given details, the objective funct...
Q: Skousen buys tennis balls at P 25 per dozen from its wholesaler. Skousen will sell 35,000 dozens of ...
A: Average number of tennis balls indicating the economic order quantity in number of balls (not in doz...
Q: Question 12 Taguchi's main approach to quality was to: O Ignore quality issues, hoping that numbers ...
A: Quality relates to the group of inherent effects of an object that permits satisfying expressed &...
Q: Describe how your mastery of project management and the concepts in this textbook will enhance at le...
A: The three employability skill that can mastery the project management concepts are:
Q: Bag Company produces leather jackets and handbags. A jacket requires of leather and a handbag only ...
A: Let, J = Units of Jackets to be produced H = Units of handbags to be produced
Q: The local driver's license center processes applications for driver's license renewals through the f...
A: Here given data:
Q: Tsinelas Corporation compares its standing to its strongest rival in the footwear industry. Tsinelas...
A: Market analysis is described as the qualitative and quantitative assessment that looks into the mark...
Q: xplain the term “Constrained Optimization” as Thaler used in the first chapter of Misbehaving.
A: Constrained optimization is used in mathematical optimization . It is the process of optimizing an o...
Q: Distinguish between the locational determinants of labor climate and quality of life.
A: The locational determinants of labour climate are linked to the labour on the other hand locational ...
Q: How much time will it take to process 85 loans?
A: Processing time per request: = Processing time of the bottleneck = Processing time of Worker 2 = 9 +...
Q: What is efficient and effective Facility Planning - Location Strategy?.
A: Facility layout is an arrangement that include different aspects of manufacturing that helps in achi...
Q: Calculate the efficiency of the newly design process.
A: A line balancing efficiency indicates the proportion between total task time and total workstation t...
Q: Normal No Spacing Replace Reu Heading 1 Fil Paragraph Styles Editing Reuse Item SKU A3378 has a dema...
A: Given data: Demand during lead time = 360 units Standard Deviation (σdLT) = 12 Stock out = 10% Servi...
Q: Based on the following Master Production Schedule, the ATP of the first week is: Week: 1 2 3 4 FC 10...
A: Given data is Beginning inventory = 145
Q: A systems specification document defines the project's scope and is sent to all key stakeholders for...
A: A systems specification document defines the system level functional and performance requirements, s...
A project
Step by step
Solved in 2 steps with 1 images
- For the following schedule, draw the arrow and node diagram. Activity Duration IPA A----3---- ABCDEFGHISKENN с H----------5------ --4- -3--- L- -6---- -3------ -9------ -1- M N----- 3636 B A -9 --A B C, D C,D E F, G, H F, G, H I J, K - GOD BLESS ---K Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) ABCDEFG B A, D C E, F Time (days) 2 7 2 10 4 5 8 This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are B-D-E-G c) The project length for the leadership training program development project = days.K Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) A BCDEF B A, D C E, F D Time (days) 4 5 3 10 5 5 10 This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are B-D-E-G. c) The project length for the leadership training program development project = days.
- Chuck’s Custom Boats (CCB) builds luxury yachts to customer order. CCB has landed a contract with a wealthy customer. Relevant data are shown in the table below. The complication is that the customer wants delivery in 32 weeks or he will impose a penalty of $375 for each week his yacht is late. Activity Immediate Predecessor Normal Time (NT) Weeks Crashing Cost 1st Week 2nd Week A ― 9 $410 $415 B A 7 125 -- C A 5 45 45 D B 4 300 350 E C 6 50 -- F D, E 5 200 225 G F 8 -- -- H F 7 85 90 I G 6 90 -- Construct a network diagram for the project Indicate the critical path when normal activity times are used. Develop a crashing schedule. Note: No activity can be crashed more than two weeks. Show breakdown of workRoger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) A C D 10 A, D 3 C Е, F 12 This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are days. c) The project length for the leadership training program development project = d) Slack time for each of the activities is: Activity Slack Time A C Enter your answer in each of the answer boxes. 251 DODDO DE EFGA B с D E FL ד G H J K L M N P R S T U V 1 On Week 3 Forecast 4 2 a) Smell Fresh Customer Orders hand 1 2 20 20 5 3 5 PAB 20 50 30 3222 4 5 6 7 8 Problem 6: Georgia Clay and Gravel was updating the MPS record for one of its products, Smell Fresh Cat Litter. Partially-completed MPS time-phased record is given below. 20 30 30 30 30 30 Week 10 30 50 20 40 10 Item: Smell Fresh On hand 1 6 Available to Promise 7 MPS 50 50 50 50 Forecast 20 8 MPS lot size = 50 9 20 10 On Week hand 2 3 4 5 6 7 8 9 20 53 43 78 30 30 30 30 30 3220 2233 -250 30 10 30 50 6 8 45 12 13 14 PAB 15 11 b) Smell Fresh Forecast Customer Orders Available to Promise 16 MPS 17 MPS lot size=50 18 19 20 21 23 24 222 Orders Projected available balance Available-to-promise MPS MPS Lot Size = 50. 50 20 40 10 50 50 50 a) Complete the MPS time-phased record (the first table on the left). The following events occurred during week 1: • Actual demand during week 1 was 25 units. • Marketing forecasted that 40 units would be needed for…
- Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) ABCDEFG B A, D C E, F Time (days) 10 62245 10 This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are A-E-G c) The project length for the leadership training program development project = days.also determined that if there are no resource constraints, the project should be complete in 30 working days. Table Q6-1: Precedence Relations and Durations for a Nine Activity Project Activity Predecessor ID A B C D E F G H I DABCDEF ID Description Site clearing Removal of trees General excavation Grading general area Excavation for trenches G H I Placing formwork and reinforcement for concrete Installing sewer lines Installing other utilities Pouring concrete Required 2 2 2 2 2 2 2 2 4 0 0 None None A A B,C B,C D,E D,E F,G 4 4 12 12 21 21 24 Table Q6-2: Resources Required and Starting Times for a Nine Activity Project Activity Workers Earliest Start Time Latest Start Time 0 9 4 15 13 2222 12 25 24 Duration (days) 4 3 [Total 2000 w 8 7 9 12 2 5 6 Given that only four workers are available for the project, determine the shortest possible time in which you can undertake this project. Draw a Gantt chart to show how you have arrived at your final schedule.K Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) A BCDEFG с II B A, D C E, F Time (days) 3 5 3 10 3 5 8 This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are B-D-E-G. c) The project length for the leadership training program development project = days. (
- Preceding Activity Crashed Cost per week $600 $700 $400 Activity Normal Completion Time (week) Crashed Completion time (week) A 7 5 B 12 10 A 8 2 $800 $300 $500 E C, D 5 4 F E 9 8 D. F 10 10 i. Draw the network diagram linking all the activities in a way that it shows if there exist any preceding activity/activities before starting each of the mentioned activities in the above table, ii. Showing the earliest start time, the earliest finish time, the latest start time and the latest finish time of each of the activities in the project determine the completion time of the project and the critical path. ii. Find the slack time (delay time) of each of the activities, the critical and the non-critical activities. Find the minimum possible completion time of the project by considering the crashed completion times and the minimal total cost of that crashing the project. iv. Need proper handwritten answers. Thank you!Q4. MRP Implementation and Entrepreneurial Thinking: a) Explain the role of Material Requirements Planning (MRP) in managing the production schedule for the product related to Central Cable Berhad (CCB). b) Identify opportunities for innovation and entrepreneurship within the project, such as exploring new materials or design features that could enhance the product's market appeal. c) Discuss how an entrepreneurial mindset can drive continuous improvement in the manufacturing process and contribute to the success of the project.Table 7.5 contains information about an environmental clean-up project in the township of Hiles. Shorten the project threeweeks by finding the minimum-cost schedule. Assume thatproject indirect costs and penalty costs are negligible. Identifyactivities to crash while minimizing the additional crash costs.