Alfred Home Construction is considering the purchase of five dumpsters and the transport truck to store and transfer construction debris from building sites. The entire rig is estimated to have an initial cost of $145,000, a life of 8 years, a $13500 salvage value, an operating cost of $40 per day, and an annual maintenance cost of $11000. Alternatively, Alfred can obtain the same services from the city as needed at each construction site for an initial delivery cost of $125 per dumpster per site and a daily charge of $26 per day per dumpster. An estimated 26 construction sites will need debris storage throughout the average year. If the minimum attractive fate of return is 10% per year, how many days per year must the equipment be required to justify its purchase? The number of days per year the equipment must be required is determined to be

Financial And Managerial Accounting
15th Edition
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:WARREN, Carl S.
Chapter26: Capital Investment Analysis
Section: Chapter Questions
Problem 5MAD: Home Garden Inc. is considering the construction of a distribution warehouse in West Virginia to...
icon
Related questions
Question
Alfred Home Construction is considering the purchase of five dumpsters and the transport truck to store and transfer construction
debris from building sites. The entire rig is estimated to have an initial cost of $145,000, a life of 8 years, a $13500 salvage value, an
operating cost of $40 per day, and an annual maintenance cost of $11000. Alternatively, Alfred can obtain the same services from the
city as needed at each construction site for an initial delivery cost of $125 per dumpster per site and a daily charge of $26 per day per
dumpster. An estimated 26 construction sites will need debris storage throughout the average year. If the minimum attractive fate of
return is 10% per year, how many days per year must the equipment be required to justify its purchase?
The number of days per year the equipment must be required is determined to be [
Transcribed Image Text:Alfred Home Construction is considering the purchase of five dumpsters and the transport truck to store and transfer construction debris from building sites. The entire rig is estimated to have an initial cost of $145,000, a life of 8 years, a $13500 salvage value, an operating cost of $40 per day, and an annual maintenance cost of $11000. Alternatively, Alfred can obtain the same services from the city as needed at each construction site for an initial delivery cost of $125 per dumpster per site and a daily charge of $26 per day per dumpster. An estimated 26 construction sites will need debris storage throughout the average year. If the minimum attractive fate of return is 10% per year, how many days per year must the equipment be required to justify its purchase? The number of days per year the equipment must be required is determined to be [
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Valuing Decision
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, finance and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Financial And Managerial Accounting
Financial And Managerial Accounting
Accounting
ISBN:
9781337902663
Author:
WARREN, Carl S.
Publisher:
Cengage Learning,
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub