Breakeven for Single Project Given: FC = 30,000.00 pesos/month v = 25.00 pesos/unit r = 35.00 pesos/unit Production = 4,320 units per month a. Breakeven Number of Units = ? b. Profit on Monthly Production = ?
Q: The question reads. A theater is presenting a program of drinking and driving for students and…
A: Let’s assume that the number of adults is x and students be y. Formulating the linear problem…
Q: The following diagram shows a 4-step process that begins with Operation 1 and ends with Operation 4.…
A: Capacity of any system is equal to its bottleneck process output
Q: Map s ipral model on any simple project
A: The winding model is a risk-driven programming advancement measure model. In light of the…
Q: it produces $40 worth of product A. Suppose also that each of the three techniques shown in the…
A: Resource Units Required Resource Price per Unit of Resource Technique 1…
Q: c. What is the expected project completion time? (Do not round intermediate calculations. Round your…
A: Expected time is calculated with the help of following formula:
Q: A contractor has a job which should be completed in 120 days. At present, he has 80 men on the job…
A: The detailed solution is given in Step 2.
Q: Answer all the following questions based on Table 2 (a) Feasibility studies for a project is an…
A: A feasibility study is an analysis used in measuring the ability and likelihood to complete a…
Q: a. How many pies must be sold in order to break even? b. What would the profit (loss) be if 1,000…
A:
Q: 4. Assume that a business firm finds that its profit is greatest when it produces $40 worth of…
A: Resource Units Required Resource Price per Unit of Resource Technique 1 Technique 2…
Q: anent b. Temporary c. Stable
A: Since the birth of civilisation, humans have taken on projects. Hunting parties in the prehistoric…
Q: The Crashing Cost/Activity for activity "D" is * $40 O $155 O $75 O $125 The "number of activity…
A: For each activity, we have immediate predecessor information, Normal time in days, crashing time in…
Q: A building contractor has a contract which will expire in 30 days. He has 80 men on the job and can…
A: The question is related to manpower planning. The details are given.
Q: A building contractor has a contract that will expire in 40 days. He has 80 men on the job and can…
A: Given Information: Contract expiry time = 40 days Current workforce hired = 80 men Completion time…
Q: a. II all other costs are assumed equal, what is the total cost for each machine for 6,000 holes,…
A:
Q: employees who work as a team on a variety of tasks; each employee works a full 40 hours a week.…
A: A Small Introduction about Management Management is the accomplishment of authoritative objectives…
Q: Just pay P10,000 per day for 30 days? Or just hire additional workers to lower down the construction…
A: A contract time indicating the duration which specified in the project that project manager must…
Q: Based on the following sensitivity report, how much should the firm be willing to pay for 160 more…
A: Sensitivity Analysis is a financial modeling tool that examines how the values of a group of…
Q: XYZ Company produces and sells 2 products, Lambda and Gamma, and the production process goes through…
A: a) Plantwide traditional approach: applied rate = Estimated m/o cost/Estimated DLH applied…
Q: Izzi used a project management softwäre package and has determined the following results for a given…
A: Expected completion time of the project: μ=22 days Variance of Project: σ2=2.77 days Standard…
Q: 1.You’re managing a project to install 400 windows in a new skyscraper and need to figure out your…
A: WIndow installation has to be done for 400 windows. Team members are paid $4,000 and $2,000 parts…
Q: Let: X1=x and X2=y Let profit=z Refer to the image: 1. What is the value of Y? 2. What are the…
A: Given Information:
Q: A project’s revenue is $40,000, and the cost is $30,000. What is the return on investment for this…
A: ROI = 40/30 = 1.33
Q: mbo Technologies has embarked on another project that has an estimated completion time of 40 weeks…
A: Given data: Completion time, μ=40 weeksStandard deviation, σ=5 weeks As we know, z=X-μσ
Q: Abloom Design Ltd is a manufacturing company that makes various types of T-shirts. The total number…
A: The question is related to Production planning. The data given in the question are Production per…
Q: The table below shows monthly data collected on production costs and on the number of units produced…
A: Given data, Month Total Production Costs Level of Activity(Units Produced)July…
Q: A manager has 5 subordinates and 5 tasks in his department. Each subordinate differs in efficiency.…
A: Find the given details below: Given details: Subordinate Task 1 2 3 4 5 A 9 10 11 8 8 B 9…
Q: Northern Engineering is analyzing a mining project. Annual production, unit costs, and unit revenues…
A: Total Cost = Annual Production * Cost per ton Total Revenue = Annual Production * price per ton
Q: In the latest earned value report for your project, the CPI is 1.1, the SPI is 0.8, the PV is…
A: Given that: CPI = 1.1 SPI = 0.8 PV = 559514 SV = $-111902.8
Q: A 4-year financial project has net cash flows of $20,000; $25,000; $30,000; and $50,000 in the next…
A: Given data; Year Cash Inflows 1 20000 2 25000 3 30000 4 50000
Q: Actual Costs for a project so far are $50,000, and the Estimate to Complete is $50,000. If a…
A:
Q: Suppose your organization is deciding which of THREE projects to bid on. The information or each is…
A: Given data is
Q: Given problem: A contractor has a job which should be completed in 120 days. At present, he has 80…
A: Given- Current workers = 80 workersEstimated completion time by the current workers = 150…
Q: The table below shows monthly data collected on production costs and on the number of units produced…
A: 1. To Calculate Variable cost per unit = higher number of units cost - lower no. of units cost…
Q: Based on the following sensitivity report, how much should the firm be willing to pay for 76 more…
A: Below is the solution:-
Q: Consider a project with an initial investment of $60,000, a 6 year useful life (and study period),…
A: Given, Initial investment = $ 60,000 Useful life = 6 years Annual revenue = $ 15,000 Salvage value =…
Q: Trex ltd want to know the expected time of the activiry G of their company and the variance of the…
A: Given: Optimistic time (a) = 4 Pessimistic time (b) = 22 Most likely time (m) = 5 To be…
Q: You are in charge of a project at the local community center. The center needs to remodel one of the…
A: Project network diagram is the visual representation of the project's activities and their duration…
Q: Source Lines of Code (SLOC) is the oldest metric for estimating project effort and thus is the…
A: Since you have asked multiple questions, we will solve the first question for you. If you want any…
Q: Normal Normal Crash Cost, $ Time 150 200 200 350 250 Crash Cost, $ 200 350 250 650 slope Time 25 150…
A: Project crashing is a procedure that uses increased charges to shorten the overall project length.…
Q: Calculate the expected time and the variance - a - 47 weeks b - 167 weeks m - 67 weeks
A: Given: Optimistic time (a) = 47 weeks Pessimistic time (b) = 167 weeks Most likely time (m) = 67…
Q: If per day indirect cost is 2000 per week, crash the following project to the point where the cost…
A: The given problem is Activity ImmediatePredecessors NormalTime NormalCost CrashTime CrashCost A…
Q: The following is a table of activities associated with a project at Ralay crash cost to reduce…
A: Network Diagram :
Q: Jse the given tasks and predecessors for this problem. The required cycle time is 25 seconds and…
A: None, Workstation 1 should only have task A assigned
Q: You are the project manager of a project that has $142590 as the budget at completion. 65% of the…
A: Given that: Budget at Completion (BAC)= $142590 Actual Cost (AC)= $78352 Planned Value (PV)= 65% of…
Q: Table on the right shows the net cashflow (NCF) and cumulative cashflow for two projects X and Y.…
A: The cumulative cash flow is a term that can be utilized for projects or an organization. Cumulative…
Q: Based on the following sensitivity report, how much should the firm be willing to pay for 53 more…
A: Given sensitivity report-
Q: A building constructor has a contract which will expire in 40 days. He has 80 men on the job and can…
A: Given:Contract expire in = 40 days 80 men can do work = 50 days The wage per day of 40 men = P 500…
Q: A company is willing to develop their rocket before the end of current financial year which is now…
A: Find the Given details below: (i) (j) Optimistic Time(To) a(Weeks) Pessimistic Time(Tp) b(Weeks)…
Q: Company X is purchasing a new machine for $949000. The annual expenses, in today's dollars, is…
A: Given values in the question are:- Initial Purchasing of new machine = $ 949900N ( project estimate…
Breakeven for Single Project
Given:
FC = 30,000.00 pesos/month
v = 25.00 pesos/unit
r = 35.00 pesos/unit
Production = 4,320 units per month
a. Breakeven Number of Units = ?
b. Profit on Monthly Production = ?
Learn your way
Includes step-by-step video
Step by step
Solved in 2 steps
- A company that makes food-friendly silicone (for use in cooking and baking pan coatings)is considering four independent projects shown, all of which can be considered to be viable for only 10 years. The company's MARR is 15% per year. Project A B C D First Cost, $ -1500 -2300 -5600 -7600 Annual net Income, $/year 200 460 1150 1200 Salvage value, $ 5 6 8 7 Determine which products to implement Financial values are in $1000 units. The present worth of project A is $___________, So project A is ___________(Rejected / Accepted) The present worth of project B is $___________, So project B is ___________(Rejected / Accepted) The present worth of project C is $___________, So project C is ___________(Rejected / Accepted) The present worth of project D is $___________, So project D is ___________(Rejected / Accepted)1.You’re managing a project to install 400 windows in a new skyscraper and need to figure outyour budget. Each week of the project costs the same: your team members are paid a total of $4,000every week, and you need $2,000 worth of parts each week to do the work. If the project isscheduled to last 16 weeks, calculate theBAC, PV, EV, AC, SPI, SV, CPI, SPI, CV for the project? 2.You’re managing a highway construction project. Your total budget is $650,000, and there isa total of 7,500 hours of work scheduled on the project. You check with your accountingdepartment, and they tell you that you’ve spent a total of $400,000. According to the schedule,your crew should have worked 4,500 hours, but your foreman says that the crew was allowed towork some overtime, and they’ve put in 5,100 hours of work. Calculate theBAC, PV, EV, AC, SPI, SV, CPI, SPI, CV for the project?WBS Element Planned Value(PV) Earned Value(EV) Actual Cost(AC) 2.01 Airframe 48000 48000 50000 2.02 Engines 22000 21000 23000 2.03 Avionics 80000 60000 45000 2.04 Communications 30000 30000 30000 2.05 Tech. Manuals 42000 42000 48000 2.06 Spares 40000 35000 42000 2.07 Training 80000 80000 86000 Project Total 342000 316000 324000 Figure 14.1 Drug Surveillance Aircraft Project - Monthly Performance Report (October 31, 20XX) Consider the project performance report presented in figure 14.1. What valid conclusion can you draw regarding the project schedule performance as of October 31, 20XX? Select one: a. The project is $26,000 behind schedule. b. The project is 18 days behind schedule. c. The project is $26,000 ahead of schedule. d. The project is $18,000 behind schedule.
- Operational Plans are preared for • a. Usually 3 months b. All of these c. Usually for 5 years d. Usually one yeartime 1 2 3 4 5 6 7 8 9 10 Returns on Project A 70.00% -24.00% 46.00% 46.00% 0.00% 9.00% -83.00% 68.00% -39.00% 112.00% Returns on Project B 63.00% -21.60% 41.40% 41.40% 0.00% 8.10% -74.70% 61.20% -35.10% 100.80% The risk of a portfolio composed of 50% in project A and 50% in project B is greater than the risk of either project A or Project B. True FalseMajor overhaul expenses of $5,000 each are anticipated for a large piece of earthmoving equipment. The expenses will occur at the end of the year four and will continue every three years thereafter up to and including year 13. The interest rate is 12% per year. a. Draw a cash-flow diagram b. What is the present equivalent of the overhaul expenses at time 0? c. What is the annual equivalent expense/annuity during only years 5-13?
- Sorin Incorporated, a company that produces and sells a single product, has provided its contribution format income statement for January. Sales (3,400 units) Variable expenses Contribution margin $ 112,200 50,490 61,710 Fixed expenses 45,700 Net operating income $ 16,010 If the company sells 3,900 units, its total contribution margin should be closest to: (Do not round intermediate calculations.) Multiple Choice $61,710 $70,785 $92,700 $18,364What adjustments to the basic breakeven calculation must be made to include target returns?2. A toy manufacturer has three different mechanisms that can be installed in a doll that it sells. The different mechanisms have three different setup costs (overheads) and variable costs and, therefore, the profit from the dolls is dependent on the volume of sales. The anticipated payoffs are as follows. Light Demand 0.25 $325,000 $300,000 -$400,000 Heavy Demand 0.3 Probability Wind-up action Pneumatic action Electrical action Moderate Demand 0.45 $190,000 $420,000 S170,000 $400,000 $800,000 $240,000 a. What is the EMV of each decision alternative? b. Which action should be selected? c. What is the expected value with perfect information? d. What is the expected value of perfect information? e. What is the expected opportunity loss?
- B. Match between column A and column B (14 Marks) A Breakeven point method Indirect cost PERT Calculate schedule Classification by Variability Depreciation and administrative expenses Project Planning/Scheduling Total float Provides contingency Difficult to establish and maintain for a large project Probability of completion before a specified date slack time СРМ Gantt ChartCompany X is purchasing a new machine for $949000. The annual expenses, in today's dollars, is estimated to be $92400. Assume that the inflation rate is 0.08 and the company X' real MARR is 0.11 per year. The depreciation for this type of machine is best represented using the declining-balance method where R= 0.29. The project is estimated to last for 9 years. a) What is the BV at year 7? b) What is the PW of these expenses? c) What is the actual value of MARR? Knowing that the project will last for 9 years, what minimum Uniform Annual Revenue, in actual dollars, would this machine need to generate to benefit?Consider a project with an initial investment of $60,000, a 6 year useful life (and study period), and a $10,000 salvage value. You expect an annual net revenue of $15,000 (before tax), a MARR before tax of 15.3%, and an effective tax rate of 35%. The capital equipment is to be depreciated using MACRS GDS and a 3 year class life. A)For the cash flow , compute after-tax MARR and evaluate the cash flow using an equivalent worth method. B) Develop the after-tax cash flows for the project of using a 4 year class life and MACRS ADS. Draw the after-tax cash flow diagram.