Current Attempt in Progress Blossom Enterprises Ltd. has entered into a contract beginning in February 2023 to build two warehouses for Bridgeport Structures Ltd. The contract is a non-cancellable fixed-price contract for $10.2 million. The following data pertain to the construction period (all figures in thousands). Costs for the year Estimated costs to complete Progress billings for the year (non-refundable) Cash collected for the year Show Transcribed Text Percent complete 2023 2023 45 % $4,230 2024 3 5,170 600 2025 5,170 3,905 4,595 1,700 3,445 4,645 2,110 Using the percentage-of-completion method, calculate the percentage complete for each year of the contract. (Round answers to O decimal places, e.g. 52%) 500 2024 -0- 94 % 2025 100 %

Financial Reporting, Financial Statement Analysis and Valuation
8th Edition
ISBN:9781285190907
Author:James M. Wahlen, Stephen P. Baginski, Mark Bradshaw
Publisher:James M. Wahlen, Stephen P. Baginski, Mark Bradshaw
Chapter9: Operating Activities
Section: Chapter Questions
Problem 18PC
icon
Related questions
Question
Current Attempt in Progress
Blossom Enterprises Ltd. has entered into a contract beginning in February 2023 to build two warehouses for Bridgeport Structures
Ltd. The contract is a non-cancellable fixed-price contract for $10.2 million. The following data pertain to the construction period (all
figures in thousands).
Costs for the year
Estimated costs to complete
Progress billings for the year (non-refundable)
Cash collected for the year
Show Transcribed Text
Percent complete
2023
2023
45 %
$4,230
5,170
2024
Ĵ
5,170
600
3,905 4,595
3,445 4,645 2,110
2025
500
Using the percentage-of-completion method, calculate the percentage complete for each year of the contract. (Round answers to 0
decimal places, e.g. 52%.)
2024
-0-
1,700
94 %
2025
100 %
Transcribed Image Text:Current Attempt in Progress Blossom Enterprises Ltd. has entered into a contract beginning in February 2023 to build two warehouses for Bridgeport Structures Ltd. The contract is a non-cancellable fixed-price contract for $10.2 million. The following data pertain to the construction period (all figures in thousands). Costs for the year Estimated costs to complete Progress billings for the year (non-refundable) Cash collected for the year Show Transcribed Text Percent complete 2023 2023 45 % $4,230 5,170 2024 Ĵ 5,170 600 3,905 4,595 3,445 4,645 2,110 2025 500 Using the percentage-of-completion method, calculate the percentage complete for each year of the contract. (Round answers to 0 decimal places, e.g. 52%.) 2024 -0- 1,700 94 % 2025 100 %
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Revenue Recognition
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Financial Reporting, Financial Statement Analysis…
Financial Reporting, Financial Statement Analysis…
Finance
ISBN:
9781285190907
Author:
James M. Wahlen, Stephen P. Baginski, Mark Bradshaw
Publisher:
Cengage Learning
Financial Accounting Intro Concepts Meth/Uses
Financial Accounting Intro Concepts Meth/Uses
Finance
ISBN:
9781285595047
Author:
Weil
Publisher:
Cengage
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
CONCEPTS IN FED.TAX., 2020-W/ACCESS
CONCEPTS IN FED.TAX., 2020-W/ACCESS
Accounting
ISBN:
9780357110362
Author:
Murphy
Publisher:
CENGAGE L