Four Squares Productions, a firm hired to coordinate of the movie Pirates of the Caribbean: On Stranger ing Johnny Depp), identified 16 activities to be com- e the release of the film. my weeks in advance of the film release should Four have started its marketing campaign? What is the crit- 2 The tasks (in time units of weeks) are as follows:

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Question 3 Four Squares Productions, a firm hired to coordinate
the release of the movie Pirates of the Caribbean: On Stranger
Tides (starring Johnny Depp), identified 16 activities to be com-
pleted before the release of the film.
a) How many weeks in advance of the film release should Four
Squares have started its marketing campaign? What is the crit-
ical path? The tasks (in time units of weeks) are as follows:
ACTIVITY
A
8
C
D
E
F
G
H
1
K
L
M
N
0
P
IMMEDIATE
PREDECESSORS
-
A
B
C
C
C
D
E
F, G, H
J, K, L
I, M
N
OPTIMISTIC
TIME
1
3
10
4
2
6
2
5
9.9
2
2
2
5
1
5
5
MOST
LIKELY
TIME
2
3.5
12
5
4
1.1
7
7
7
4
7.7
10
4
4
4
6
PESSIMISTIC
TIME
13
7
5
8
5.5
9
12
5
6
6
65
2
8
9
b) If activities I and J were not necessary, what impact would this
have on the critical path and the number of weeks needed to
complete the marketing campaign?
Transcribed Image Text:Question 3 Four Squares Productions, a firm hired to coordinate the release of the movie Pirates of the Caribbean: On Stranger Tides (starring Johnny Depp), identified 16 activities to be com- pleted before the release of the film. a) How many weeks in advance of the film release should Four Squares have started its marketing campaign? What is the crit- ical path? The tasks (in time units of weeks) are as follows: ACTIVITY A 8 C D E F G H 1 K L M N 0 P IMMEDIATE PREDECESSORS - A B C C C D E F, G, H J, K, L I, M N OPTIMISTIC TIME 1 3 10 4 2 6 2 5 9.9 2 2 2 5 1 5 5 MOST LIKELY TIME 2 3.5 12 5 4 1.1 7 7 7 4 7.7 10 4 4 4 6 PESSIMISTIC TIME 13 7 5 8 5.5 9 12 5 6 6 65 2 8 9 b) If activities I and J were not necessary, what impact would this have on the critical path and the number of weeks needed to complete the marketing campaign?
Expert Solution
steps

Step by step

Solved in 6 steps with 7 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.