In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Revenue Gross profit (loss) $ $ Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. Note: Do not round intermediate calculations. Loss amounts should be indicated with a minus sign. 2024 2,800,000 728,000 2024 $ 2,072,000 5,328,000 2,160,000 1,880,000 2025 2025 $ 2,738,000 2,590,000 2,650,000 2,700,000 2026 2026 $ 2,849,000 0 5,190,000 5,420,000

CONCEPTS IN FED.TAX.,2020-W/ACCESS
20th Edition
ISBN:9780357110362
Author:Murphy
Publisher:Murphy
Chapter3: Income Sources
Section: Chapter Questions
Problem 88P
icon
Related questions
Question
Do not give image format
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2026. Information related to the contract is as follows:
Cost incurred during the year
Estimated costs to complete as of year-end
Billings during the year
Cash collections during the year
Westgate recognizes revenue over time according to percentage of completion.
Required:
1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years.
Note: Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.
Revenue
Gross profit (loss)
$
$
2024
2,800,000
728,000
2024
2025
2026
$ 2,072,000 $ 2,738,000 $ 2,849,000
5,328,000
2,590,000
2,650,000
2,160,000
1,880,000
2,700,000
2025
2026
0
5,190,000
5,420,000
Transcribed Image Text:In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. Note: Do not round intermediate calculations. Loss amounts should be indicated with a minus sign. Revenue Gross profit (loss) $ $ 2024 2,800,000 728,000 2024 2025 2026 $ 2,072,000 $ 2,738,000 $ 2,849,000 5,328,000 2,590,000 2,650,000 2,160,000 1,880,000 2,700,000 2025 2026 0 5,190,000 5,420,000
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Knowledge Booster
Accounting for Long-Term contracts
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
CONCEPTS IN FED.TAX., 2020-W/ACCESS
CONCEPTS IN FED.TAX., 2020-W/ACCESS
Accounting
ISBN:
9780357110362
Author:
Murphy
Publisher:
CENGAGE L
Intermediate Accounting: Reporting And Analysis
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning