Job times which includes processing and set up times are shown below:
Job Job Time (brs)
Due Date (bs)
15
24
20
AMUO
А
B
C
12
6
14
3
7
D
B
Using FCFS, determine the average tardiness
6
Transcribed Image Text:Job times which includes processing and set up times are shown below: Job Job Time (brs) Due Date (bs) 15 24 20 AMUO А B C 12 6 14 3 7 D B Using FCFS, determine the average tardiness 6
Expert Solution
steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,