op a project network Activity-on-Arrow (AOA) for the club’s tournament preparation process and show all activity schedule and duration of the project [show clearly all dummy activities] kindly show a clear activity pn arrow networking drawing for this.
Activity |
Description |
Predecessor |
Duration (Days) |
A |
Send application forms |
– |
7 |
B |
Get volunteer workers |
– |
18 |
C |
Line up referees |
– |
10 |
D |
Reserve fields |
– |
21 |
E |
Receive and process forms |
A |
30 |
F |
Determine age divisions |
B, C, D, E |
9 |
G |
Assign fields to divisions |
F |
7 |
H |
Sell program ads |
B |
2 |
I |
Acquire donated items for team gift bags |
B |
20 |
J |
|
G |
14 |
K |
Design ads |
H |
80 |
L |
Fill gift bags |
I |
12 |
M |
Process team t-shirt orders |
E |
10 |
N |
Send acceptance letters |
F |
7 |
O |
Design and print programs |
J, K, L, N |
18 |
P |
Put together registration boxes (programs, gifts, etc.) |
O |
7 |
Q |
Send out game schedules |
J, K, L, N |
8 |
R |
Assign referees to games |
J, K, L, N |
7 |
S |
Get trophies |
F |
8 |
T |
Silk-screen t-shirts |
M |
17 |
U |
Package team t-shirt orders |
T |
8 |
a) Develop a project network Activity-on-Arrow (AOA) for the club’s tournament preparation process and show all activity schedule and duration of the project [show clearly all dummy activities]
kindly show a clear activity pn arrow networking drawing for this.
Step by step
Solved in 2 steps with 1 images