Problem 1 The F/C production line manufactures the Flask/cap product. Demand for this product is 57K, 35K and 80K for weeks 5, 6, and 7 respectively. The Flask/cap product is painted and assembled in work area 1, while the Base flask and the Cap components are both molded in work area 2. The RXY plastic is a purchased item. Current time: start of week 1. The available total weekly capacity for work areas 1 and 2 are 1,000 and 800 hours respectively. 1. Determine the release plan for the end item and purchased components. 2. Determine if there is sufficient capacity for the plan. Item OH Lot Size or Lead Prod. Time Minimum Time Flask/cap LFL 1 1min Base flask 32K Min: 40K 1 20 sec 16K 9 sec Cap RXY plastic LS: 50K 1 590K oz. LS: 600K oz. NA 2.

Marketing
20th Edition
ISBN:9780357033791
Author:Pride, William M
Publisher:Pride, William M
Chapter19: Pricing Concepts
Section: Chapter Questions
Problem 6DRQ
icon
Related questions
Question
Operations Management
MRP Problems
Problem 1
The F/C production line manufactures the Flask/cap product. Demand for this
product is 57K, 35K and 80K for weeks 5, 6, and 7 respectively. The Flask/cap
product is painted and assembled in work area 1, while the Base flask and the
Cap components are both molded in work area 2. The RXY plastic is a
purchased item. Current time: start of week 1. The available total weekly
capacity for work areas 1 and 2 are 1,000 and 800 hours respectively.
Flask/cap
1. Determine the release plan for the end item and purchased
components.
Determine if there is sufficient capacity for the plan.
Саp
2.
Item
ОН
Lot Size or
Lead
Prod. Time
Base flask
RXY plastic
2 oz
Minimum
Time
Flask/cap
LFL
1
1min
RXY plastic
7 oz
Base flask
32K
Min: 40K
1
20 sec
LS: 50K
9 sec
Сар
RXY plastic
16K
1
590K oz.
LS: 600K oz.
2
NA
Problem 2
The foam car production line manufactures two models:
Transcribed Image Text:Operations Management MRP Problems Problem 1 The F/C production line manufactures the Flask/cap product. Demand for this product is 57K, 35K and 80K for weeks 5, 6, and 7 respectively. The Flask/cap product is painted and assembled in work area 1, while the Base flask and the Cap components are both molded in work area 2. The RXY plastic is a purchased item. Current time: start of week 1. The available total weekly capacity for work areas 1 and 2 are 1,000 and 800 hours respectively. Flask/cap 1. Determine the release plan for the end item and purchased components. Determine if there is sufficient capacity for the plan. Саp 2. Item ОН Lot Size or Lead Prod. Time Base flask RXY plastic 2 oz Minimum Time Flask/cap LFL 1 1min RXY plastic 7 oz Base flask 32K Min: 40K 1 20 sec LS: 50K 9 sec Сар RXY plastic 16K 1 590K oz. LS: 600K oz. 2 NA Problem 2 The foam car production line manufactures two models:
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Forecasting methods
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Marketing
Marketing
Marketing
ISBN:
9780357033791
Author:
Pride, William M
Publisher:
South Western Educational Publishing