The following CPM/PERT network represents a small project with 4 activities labelled A through D. The activity times (in days) are provided in the table. Activity Time B 21 C 8 D 12 There's a diagram in the associated PDF file that you can print out and use to answer the following questions. The available slack (S) for Activity C is 57.33 5.
Q: A construction project is broken down into the following activities Activity Immediate predecessor…
A: Network diagram is given by From the network diagram, we have four paths, namely, 1-2-5-8-10…
Q: Conslder the AON graph of a project shown below. 12 A4 A3 Figure 19.17 A6 02:25:04 Ag A7 A2 A1 A5…
A: Find critical path The total time of all the critical activity is the Project completion time
Q: There is a running project in the company that you work for, which has the following activities:…
A: Given data is
Q: The figure shows the network diagram of a project along with the activity durations (T). In this…
A: A project schedule network diagram shows the sequential and analytical connection between tasks in a…
Q: The activities described by the following table are given for the Howard Corporation in Kansas Time…
A: This question is related to the topic Project Management and This topic falls under Operations…
Q: a) Based on the activity time estimates, the expected times and variance for each of the…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: The activity times are 3, 4, 2, 5, 7, 2, 2, and 3 days for activities A1 through A8,respectively.…
A:
Q: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine.…
A: Network diagram:
Q: A project has been defined to contain the following activities, along with their time estimates for…
A: The Critical path diagram of the given activities as follows -
Q: Consider the following table and answer the following questions. All duration estimates or estimated…
A: Activity on arrow and activity on node both are different concept, in AOA we use circle diagrams…
Q: A project schedule has the following characteristics as shown in table 2 Table 2 Activities 1-2 |…
A: AON diagram
Q: Consider Table 6-3. All duration estimates or estimated times are in weeks, and the network proceeds…
A: The question is related to Critical Path Analysis. The details are given regarding activities and…
Q: A project network is shown below. Use a forward and a backward pass to determine the critical path,…
A:
Q: The project detailed in the table below is contracted for delivery in 11 weeks, with a penalty…
A: A project network diagram is a graphic depiction of a project's process. A network diagram is a…
Q: Draw the network diagram based on the information given below. Calculate the ES, EF, LS, LF and…
A: 1. During forward pass in case of more than two preceding activities the early start will be…
Q: The activities in the following table describe the construction of a new house. Construct the…
A: This question is related to the topic -Project management and this topic falls under the business…
Q: Consider the AON graph of a project shown below. A4 Figure 19.17 A3 A6 (A8 (A7 A2 A1 A5 The activity…
A: in order to find the earliest competition time from the activity-on-node diagram above, we need to…
Q: Schedules and activities of some projects are shown below Draw the network diagram Activity…
A: I will be drawing the network diagrams for the 2 projects. Please post it again for other projects'…
Q: Construct a Gantt chart for the following set of activities and indicate the project completion…
A:
Q: For each of the following network diagrams, determine both the critical path and the expected…
A: b. The possible paths are: 1-2-4-6-8-9: = 5 + 18 + 3 + 4 + 9 2 = 41 weeks 1 - 2 - 5 - 6 - 8 - 9 = 5…
Q: Early Start, Early Finish, Late Start, Late Finish, Duration, Float Below is a project listed in a…
A: Given- Activity Predecessor Duration (Weeks) A None 5 B A 3 C A 8 D C 13 E B 7 F B 9…
Q: You are creating a customer database for the Lehigh Valley IronPigs minor league baseball team. a)…
A: Below is the solution:-
Q: A project requires these activities to be completed and the table below shows the expected time and…
A: It can see that the cost variance is positive. While the scheduled variance is negative. The…
Q: PERT-CPM Maurice Publishing Inc. has a contract with Joan who authored the manual “Basics of…
A: Given data is
Q: Dave Fletcher was able to determine the activity times for constructing his laser scanning machine.…
A: For each activity, I have Time data and immediate predecessors' data, I would determine the…
Q: For the following schedule, draw the node network, perform the CPM calculations, mark the critical…
A: below is the solution:-
Q: For the project data in Table below, answer the following questions: a) Draw AON & AOA networks of…
A: Below is the solution:-
Q: Activities, preceding activities, normal and crashed completion times of each of the activities and…
A: Forward Pass: Early Start (ES) = Maximum EF value from immediate Predecessor(s) Early Finish (EF) =…
Q: a) Calculate each activity duration using the last digit of your student number For example, if your…
A: Below is the solution:-
Q: accompanying Table 1 shows the activities, times and sequences required for the project planning and…
A: the critical path is a step by step technique to identify the critical activities in the project.…
Q: Activity Preceding Activity Expected Completion Time (in Weeks) A None B A 2 A D B 12 E D 10 F 9 D H…
A: Activity Immediate Predecessors Duration A - 5 B A 2 C A 6 D B…
Q: a) The expected (estimated) time for activity C is 12.00 weeks. (Round your response to two decimal…
A: To determine the Estimated time for any activity, we would use the below formula, the expected time…
Q: 2. | Jean Walker is making plans for spring break at the beaches in Florida. In applying techniques…
A: Given data is
Q: an the following table the activities with their precedence sequence and expected time (days) are…
A: Network Diagram :
Q: Before answering the following questions, you must draw the arrow diagram, rectangles, network…
A:
Q: A simple CPM network has three activities, G, H, and I. G is an immediate predecessor of H and of I.…
A: ANSWER IS AS BELOW:
Q: You are given the activity information below and the activity-on-node precedence diagram for a…
A: An organization chart has numerous ways beginning from one point and finishing at another point.…
Q: The following table contains a list of activities, with precedence requirements and crash costs. All…
A: a.
Q: A project consists of seven activities, lettered A through F below. For each activity, the estimated…
A: The question is related to Crashing. The cost slope will be calculated for each activity with the…
Q: Use the Program Evaluation and Review Technique to represent the project in an activity network. In…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: 2. Draw an AON network diagram and calculate its early start, early finish, late start and late…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: Project ALPHA has 6 activities from A to Fas follows: Activity Duration Preceded By B A D Legend:…
A: Given data is
Q: A network consists of the activities in the following list. Times are gi Activity Preceding Time А 8…
A: Network Diagram-
Q: the network consists of the following list. Times are given in week. 1. draw the network diagram.…
A: Given data, Activity Preceding Optimistic Probable Pessimistic A -- 5 11 14 B -- 3 3 9 C --…
Q: a) Calculate each activity duration using the last digit of your student number. For example, if…
A: THE ANSWER IS AS BELOW:
Q: Project Management In the below Precedence Diagram ( The activities durations are in weeks ) If…
A: Here, in the question, we have Network diagram, for each activity node, I have following data like…
Q: Activity Immediate Predecessor Time A 5 B A 8. B D A 8 9. F C 2 G D, E H F 7 G 4 H, I 3
A: Given activities-
Q: For the following simple seven‐activity project, develop a precedence network, calculate all…
A: : Since we only answer up to 3 sub-parts, we’ll answer the first 3. Please resubmit the question and…
Q: The network dlagram and task times for a project are shown below. A2 A4 A5 A3 Task Duration (days)…
A: Using Forward Path, find Early Start of the activity = Early Finish of predecessor activity Early…
Q: A simple CPM network has three activities, N, O, and P. N is an immediate predecessor of O and of P.…
A: ANSWER IS AS FOLLOW:
Step by step
Solved in 2 steps with 3 images
- Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: a. the critical activities for the leadership training program development project are: _____ b. the project length for the leadership training program development project= __ days. c. Slack time for each of the activities is: Activity: Slack time: A ______ B ______ C ______ D ______ E ______ F ______ G ______The following represents a project that should be scheduled using CPM: IMMEDIATE PREDECESSORS ACTIVITY A ABCDEFGH B-E-G-H b. What is the critical path? A-C-F-H OA-D-F-H A-D-G-H A A B C,D D, E F,G Project completion time a LLL23312 TIMES (DAYS) m •WNNW: 3 2 2 3 4 4 4 4 b 5 3 3 4 11 c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 2 decimal places. days 565The following activities are part of a project to be scheduled using CPM: TIME (WEEKS) 7 6 ACTIVITY IMMEDIATE PREDECESSOR A BCDEFG O A-C-D-E-G O A-B-E-G O A-C-D-F-G O A-B-D-F-G AACB A Number of weeks A b. What is the critical path? B, D D E, F 24346 c. How many weeks will it take to complete the project?
- Shown below is the project network diagram for a small office renovation project. The numbers in the nodes are the activity times. What is the slack time for activity A? 7 5 3 0Activities, preceding activities, normal and crashed completion times of each of the activities and crashed costs of activities per week of a project are given in the following table. Activity Preceding Activity Normal Crashed Completion time (week) Crashed Cost Completion Time (week) 7 per week A 7 B $500 C 4 3 $700 $600 A A, C В, D D, E D 7 E F 10 9. $800 9 8 $400 i. Draw the network diagram linking all the activities in a way that it shows if there exist any preceding activity/activities before starting each of the mentioned activities in the above table. ii. Find the earliest start time, the earliest finish time, the latest start time and the latest finish time of each of the activities in the drawn diagram of the project and hence the completion time of the project and the critical path.The information in the table below is available for a large fund-raising project. Activity Activity Times (days) Activity Cost ($) Immediate Predecessor A 3 100 None B 4 150 None C 2 125 A D 5 175 B E 2 150 B F 4 200 C, D G 6 75 C H 2 50 C, D, E I 1 100 E J 4 75 D, E K 5 350 F, G L 3 150 G, H, I M 4 400 I, J N 4 175 K, M O 1 200 H, M P 5 150 N, L, O Draw the precedence network diagram. Perform the CPM (Critical Path Method) and give the complete activity schedule table, the project completion time, and the critical path. Plot on the same graph the total project costs per day, starting from day one to the completion date, assuming the earliest start times and then assuming the latest start times. What implications does the time differential have for cash flows and project scheduling? Show step by step solution
- Critical Path Method (CPM) helps project manager to plan all tasks that must be completed as part of a project. They act as the basis both for preparation of a schedule, and of resource planning. A further benefit of CPM is that it helps to identify the minimum length of time needed to complete a project. Given the following task lists for planning a custom-written computer project as in Table 1: Table 1: Task List Task Length Predecessor A. High level analysis 1 week B. Selection of hardware platform 1 day A C. Installation and commissioning of hardware 2 weeks B D. Detailed analysis of core modules 2 weeks A E. Detailed analysis of supporting modules 2 weeks D F. Programming of core modules 2 weeks D G. Programming of supporting modules 3 weeks E H. Quality assurance of core modules 1 week F 1. Quality assurance of supporting modules 1 week G J.Core module training 1 day C,H K. Development and QA of accounting reporting 1 week E L. Development and QA of management reporting 1 week M.…The table below show a set of activities of an IS project,its expected completion time (ET) and preceding activities. Activity Preceding Activity Expected Time (ET) A - 7 B A 9 C A,B 5 D C 17 E C 12 F C 7 G D,E,F 10 H D,G 7 Draw a network diagram for the IS project shown above.,and calculate its earliest completion time (TE), latest completion time (TL) and slack time (ST). If the activity E took 16weeks instead of 12weeks to complete ,what impact will it have on the project duration?The following represents a project that should be scheduled using CPM: ACTIVITY A B C D E F G H IMMEDIATE PREDECESSORS A A B C, D D, E F,G b. What is the critical path? ⒸA-D-G-H OB-E-G-H ⒸA-C-F-H A-D-F-H Probability TIMES (DAYS) b Project completion time a 1 1 2 1 1 3 1 2 m 2 2 2 8 2 4 3 3 6 9 11 9 3 c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. 11 11 11 X Answer is not complete. days d. What is the probability of completing this project within 19 days? Note: Use Excel's NORM.S.DIST function to find the correct probability for your computed Z value. Do not round intermediate calculations. Round Z value to 2 decimal places and final answer to 4 decimal places.
- Colonial State College is considering building a new multipurpose athletic complex on campus. The complex would provide a new gymnasium for intercollegiate basketball games, expanded office space, classrooms, and intramural facilities. The following activities would have to be undertaken before construction can begin. Activity A B C D E F G H IMG_A2D52FAF8F3D-1.jpeg Activity This answer has not been graded yet. A B с (c) Develop the activity schedule for the project. D Survey building site Develop initial design Obtain board approval E F G Description H Select architect Establish budget Finalize design Obtain financing 0 Hire contractor L L | (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) Choose File No file chosen Immediate Predecessor Earliest Start (b) Identify the critical path. (Enter your answers as a comma-separated list.) 4 A, B с Latest Start с D, E E F, G Time (weeks) 5 5 9 Earliest Finish 13 4 7 15 11 6 9 Latest Finish 4 Slack (d) Does it appear…Relevant information for a project consisting of activities A, B, ..., K is provided in the table below and the project network is provided. Activity Time in Weeks Immediate Predessors A 2 ΝΑ B C D E F G H I J K 7 7 6 2 2 7 7 2 6 5 The project network is: ΝΑ A, B C с E C D, F, G D, F H I, J What is the minimum number of weeks that the project can be completed in (i e. the duration of the critical path)?Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity A B с D Time (weeks) 5 8 2 1 Immediate Predecessor(s) A A Dave's earliest start (ES) and earliest finish (EF) are: Activity A Activity EFGH ES Time (weeks) 3 EF 5 5 10 7 Immediate Predecessor(s) B B C, E D, F