The standard and actual cost data of RIZWAN LTD. are as follows: Standard Actual 68,600units @ Rs. 24.50 42,000 hrs @ Rs. 45.50 Direct Material 70,000 units @ Rs. 28 Direct Labour 35,000 hrs @ Rs. 42 50% of direct labour Factory Overhead Rs. 94,500 Required: a) Calculate i) Material price variance and material quantity variance ii) Labour rate Variance and labour time variance iii) Overhead variance b) General journal entries to record the above information and to close the variance accounts.

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter8: Standard Costs And Variances
Section: Chapter Questions
Problem 9PB: Ribcos labor cost information for making its only product for March is as follows: A. What is the...
icon
Related questions
Topic Video
Question
The standard and actual cost data of RIZWAN LTD. are as follows:
Standard
Actual
68,600units @ Rs. 24.50
42,000 hrs @ Rs. 45.50
Direct Material
70,000 units @ Rs. 28
35,000 hrs @ Rs. 42
Direct Labour
Factory Overhead
50% of direct labour
Rs. 94,500
Required:
a) Calculate
i)
Material price variance and material quantity variance
ii) Labour rate Variance and labour time variance
iii) Overhead variance
b) General journal entries to record the above information and to close the variance accounts.
Transcribed Image Text:The standard and actual cost data of RIZWAN LTD. are as follows: Standard Actual 68,600units @ Rs. 24.50 42,000 hrs @ Rs. 45.50 Direct Material 70,000 units @ Rs. 28 35,000 hrs @ Rs. 42 Direct Labour Factory Overhead 50% of direct labour Rs. 94,500 Required: a) Calculate i) Material price variance and material quantity variance ii) Labour rate Variance and labour time variance iii) Overhead variance b) General journal entries to record the above information and to close the variance accounts.
The following are actual cost and variances for direct materials and cirect labour for the month of March 2002:
Actual
Variances
Cost
Unfavorable
Favorable
Rs.
Rs.
Rs.
Direct Material
450,000
Price variance
35,000
Quantity Variance
25,000
Direct Labour
800,000
Rate variance
22.500
Efficiency variance
52,500
Required:
Standard cost of direct materal and direct labour
Entries in the general joumal to record the above information and to close the variance accOunts
Transcribed Image Text:The following are actual cost and variances for direct materials and cirect labour for the month of March 2002: Actual Variances Cost Unfavorable Favorable Rs. Rs. Rs. Direct Material 450,000 Price variance 35,000 Quantity Variance 25,000 Direct Labour 800,000 Rate variance 22.500 Efficiency variance 52,500 Required: Standard cost of direct materal and direct labour Entries in the general joumal to record the above information and to close the variance accOunts
Expert Solution
steps

Step by step

Solved in 3 steps with 4 images

Blurred answer
Knowledge Booster
Performance measurements
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Managerial Accounting: The Cornerstone of Busines…
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning
Principles of Cost Accounting
Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning