to the attached image. pls show formula and solution in manual calculation. 1. NPV of Project Z? 2. Payback period of Project X? 3. Payback period of Project Y? 4. Payback period of pro
Q: The TELOS study that determines whether a project can be completed in an acceptable time frame isa.…
A: TELOS: TELOS stands for Technical, Economic, Legal, Operational and Schedule feasibility. It is the…
Q: a. Calculate the projects’ NPVs, IRRs, MIRRs, regular paybacks, and discounted paybacks. b. If the…
A: Note : As per the bartelby guidelines only first two parts will be answered. Given information :
Q: A. Calculate the net present value of each of the projects. Which project should Ben invest in? Show…
A: Answer: A Whichever project has the higher NPV is the more profitable and should be a priority and…
Q: discusses the acronym TELOS which provides guidance for accessing project feasibility. The term…
A: Cost: Cost can be defined as the cash and cash equivalent which is incurred against the products…
Q: equired: Calculate the project's net Without making any calcul
A: NPV = Present value of cashinflows - Present value of cashoutflows.
Q: he payback period for each project The Net Present Value (NPV) The Profitability index Which project…
A: Formulas:
Q: requirea: 1. Compute the project profitability index for each project. ord
A: Profitability Index = (Net Present Value + Initial Investment)/Initial Investment…
Q: Discuss which tools you would use to decide whether a project is worthy of financing? Also,…
A: net present value is the tool used to decide that a project is worthy of financing net present value…
Q: Requirements 1. Determine the payback period of each project. Rank the projects from most desirable…
A: Payback period is a technique of capital budgeting to find out the time period in which the initial…
Q: Answer this question as it is pertaining to two MUTUALLY EXCLUSIVE projects on the following figure.…
A: IRR internal rate of return is where net present value is zero.
Q: Evaluate the projects using each of the following criteria, stating which project(s) Carrium…
A: Information Provided: Required rate = 11% Expand (CF) Purchase Equipment (CF) 0 (400,000)…
Q: Suppose that your organization wants to decide which one of the given two projects can be…
A: The computations as follows: Hence, the EMV of project 1 is $36000.
Q: Calculate the Payback period and discounted pay back period of these projects! Which project should…
A: The capital budgeting is a tool or technique that helps to analyze the overall profitability of the…
Q: What's the discount payback period of the projects? (compile a spreadsheet) Calculate NPV, PI of a…
A: The discounted payback period is the time required for a project to return its initial investment.…
Q: The following table contains information about four projects in which Morales Corporation has the…
A: Accounting Rate of Return will be ranked from highest to lowest.
Q: Evaluate the projects using each of the following criteria, stating which project(s) Insignia…
A: Payback period is the time taken by project cash inflows to recover initial investment. Discounted…
Q: Please calculate the Net present value for Project A and B in the way shown on photo (only shown as…
A: Here, Discount Rate is 10%
Q: Rank the projects according to the NPV, IRR and B/C investment criteria; NPV $6.36 $11.32 IRR 33%…
A: Net present value (NPV) is the value of all the cash flow of the investment (positive and negative)…
Q: NPV (TL) A Project B Project 750 1000 1250 1500 1750 0.1 0.15 0.2 0.25 0.3 0.15 0.25 0.3 0.1 0.2
A: The question is based on the concept of calculation of expected value ,standard deviation and…
Q: 3- This question relates to the diagram, which shows the NPV profile for Projects X and Y. What is…
A: The internal rate(IRR) of Return is the rate of cost of capital at which the NPV of the project is…
Q: Build an Excel Model to compute the NPV of investment project I or II and make sure that the model…
A: Hi There, Thanks for posting the questions. As per our Q&A guidelines, must be answered only one…
Q: Use the information below and help the management in choosing the most desirable Project using a.…
A: Capital budgeting is referred as the process of decision making which is used by companies to…
Q: You are analyzing a project and have prepared the following data: a. Based on the net present…
A: IRR is the rate at which NPV is zero.
Q: Under what circumstances will you prefer profitability index to NPV as project evaluation…
A: Capital budgeting analysis is useful to know which projects are profitable and which are not. There…
Q: d. What is the profitability index for each project? (Do not round intermediate calculations and…
A: Discount rate is 12% To Find: Profitability Index
Q: A firm evaluates all of its projects by applying the IRR rule. a. What is the project's IRR? (Do…
A: Required return is 15% To Find: IRR of the project Acceptance of project
Q: t are the problems in using the Internal Rate of Return method when making decisions on which…
A: Internal rate of return is rate at which present value of cash flow is equal to the initial…
Q: Compute for the payback periód öf éåch project hich project will you choose and why? Show solution.…
A: The payback period for all the three project can be calculated as follows:
Q: n WACC can be used as the project's required return
A: Required rate of return is the minimum benefits that can be obtained from undertaking a project.
Q: a. Determine the payback period for each machine. b. Comment on the acceptability of the machines,…
A: Information Provided: Machine 1: Annual cash flow = $3000 Initial Investment = $14,000 Term = 7…
Q: choosing the most desirable Project using Payback period а. b. Discounted payback c. Net Present…
A: The calculations and the steps can be seen below:
Q: Payback is best used to evaluate which types of project
A: Payback period is used to calculate the period in which our cash inflows will get equal to our cash…
Q: eda Enterprises has the option to invest in machinery in projects A and B but finance is only…
A: Payback period is the time taken to recover the initial cost of investment. Payback period considers…
Q: Requirements 1. Determine the payback period of each project. Rank the projects from most desirable…
A: Payback Period is the period in which the amount of Initial Investment can be recovered. Project…
Q: Critically discuss the Expected Net Present Value method (ENPV) and explain why it may be more…
A: Expected Net Present Value method is a method of capital budgeting. Under this method it is…
Q: When evaluating a project, the best metrics to use are: Question 42 options: NPV and payback…
A: There were various financial techniques were followed to evaluate a project. Some are payback…
Q: Selection of Project Time Value of Money Investment Criteria
A: Selection of Project is based on certain factors which are sub-categorized as- mission, process,…
Q: You have been assigned to perform a project selection based on profitability index. You have…
A: Profitability Index: It is a capital budgeting technique in which projects are ranked according to…
Q: (a) Calculate the payback period of each project. ( ) (b) Compute the net present value of the two…
A: Payback Period: It is the period in which the project returns its initial outlay/cost. The lower…
Q: a. calculate the payback period for each project. b. calculate the net present value for each…
A: Payback period is the time required to recover the cost of investment. Payback period = ((Year of…
Q: (c) Internal Rate of Return (IRR);
A: (A) Pay back period Year Project A Cumulative Cash Flow A Project B 1 9700 9700 5200 2 8500…
Q: Based on the picture, Calculate: a) The payback period for the project b) The discounted payback…
A: The payback period is a capital budgeting method that represents the liquidity position of a project…
Q: How many IRRs could be estimated for each project below: Project A has ________ (1, 2.3. or 4)…
A: Internal rate of return is defined as the metric, which is generally used in the financial analysis…
Q: You are requested to assess the projects using payback period method and suggest the director on the…
A: The payback period is the most common tool for evaluation of the investments and decision making of…
Q: QUESTION) Calculate the Accounting Rate of Return (on average investment) of Project B (expressed to…
A: Accounting rate of return is a ratio in capital budgeting that does not take into account the time…
Q: ject a project. Your should refer to all four investment appraisal methods.
A: Capital budgeting is used to decide whether a project should be accepted or rejected. Capital…
Q: Given mutually exclusive projects, which project should be selected given the MARR- 9%? Note that…
A: Before investing in new projects or investments, profitability is evaluated by using various methods…
Pls refer to the attached image.
pls show formula and solution in manual calculation.
1.
2. Payback period of Project X?
3. Payback period of Project Y?
4. Payback period of project Z?
5. Based on the calculated NPV and payback period, which project would you recommend and why? Include the implications of projects' NPVs and payback period in your explanation.
Step by step
Solved in 2 steps with 2 images
- Bruin, Incorporated, has identified the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 −$ 66,000 −$ 66,000 1 42,000 28,400 2 36,000 32,400 3 24,000 38,000 4 15,200 24,400 a-1. What is the IRR for each of these projects? a-2. If you apply the IRR decision rule, which project should the company accept? b-1. Assume the required return is 12 percent. What is the NPV for each of these projects? b-2. Which project will you choose of you apply the NPV decision rule? c-1. Over what range of discount rates would you choose Project A? c-2. Over what range of discount rates would you choose Project B? d. At what discount rate would you be indifferent between these two projects?Bruin, Incorporated, has identified the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 −$ 28,500 −$ 28,500 1 13,900 4,050 2 11,800 9,550 3 8,950 14,700 4 4,850 16,300 a-1. What is the IRR for each of these projects? a-2. Using the IRR decision rule, which project should the company accept? multiple choice 1 Project A Project B a-3. Is this decision necessarily correct? multiple choice 2 Yes No b-1. If the required return is 11 percent, what is the NPV for each of these projects? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) b-2. Which project will the company choose if it applies the NPV decision rule? multiple choice 3 Project A Project B c. At what discount rate would the company be indifferent between these two projects? (Do not round intermediate…Piercy, LLC, has identified the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) -$56,000 32,000 26,000 19,000 13,200 -$56,000 19,400 23,400 28,000 25,400 1 3. 4. a-1. What is the IRR for each of these projects? (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) a-2. If you apply the IRR decision rule, which project should the company accept? b-1. Assume the required return is 12 percent. What is the NPV for each of these projects? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g.., 32.16.) b-2. Which project will you choose of you apply the NPV decision rule? c-1. Over what range of discount rates would you choose Project A? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) c-2. Over what range of discount rates would you choose Project B? (Do not round intermediate calculations and…
- Bruin, Inc., has identified the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) -$29,700 -$29,700 15,100 4,650 13,000 10,150 9,550 15,900 5,450 17,500 0123 + 4 a-1 What is the IRR for each of these projects? (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) Project A Project B a-2 Using the IRR decision rule, which project should the company accept? Project A O Project B % % 2 lo this decisi orrectAssume a $6,500 investment and the following cash flows for two alternatives. Year Investment X Investment Y 1 $ 1,000 $ 1,300 2 1,800 2,000 3 1,700 1,100 4 2,000 1,500 5 600 Under the payback method, which of the following could be concluded?Bruin, Incorporated, has identified the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 −$ 28,000 −$ 28,000 1 13,400 3,800 2 11,300 9,300 3 8,700 14,200 4 4,600 15,800 a-1. What is the IRR for each of these projects? (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) b-1. If the required return is 10 percent, what is the NPV for each of these projects? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) c. At what discount rate would the company be indifferent between these two projects? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.)
- ZumBahlen Inc. is considering the following mutually exclusive projects: Year 0 1 2 3 4 Project A Cash Flow -$5,000 O a. 16.15% O b. 20.15% O c. 18.15% O d. 22.15% 200 800 Project B Cash Flow -$5,000 3,000 3,000 3,000 5,000 At what cost of capital will the net present value of the two projects be the same? (That is, what is the "crossover" rate?) 800 200Bruin, Incorporated has identified the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 -$ 41,300 1 19, 100 2 17,800 3 15, 200 4 8,400 -$ 41,300 6,300 14, 200 17,900 30,300 a-1. What is the IRR for each of these projects? Note: Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16. a-2. If you apply the IRR decision rule, which project should the company accept? b-1. Assume the required return is 11 percent. What is the NPV for each of these projects? a-1. Project A Project B a-2. Project acceptance b-1. Project A Project B b-2. Project acceptance Note: Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16. b-2. Which project will you choose if you apply the NPV decision rule? % %Bruin, Incorporated, has identified the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 -$ 61,000 -$ 61,000 1 37,000 23,900 31,000 27,900 21,500 33,000 4 14,200 24,900 a-1. What is the IRR for each of these projects? Note: Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16. a-2. If you apply the IRR decision rule, which project should the company accept? b-1. Assume the required return is 12 percent. What is the NPV for each of these projects? Note: Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16. b-2. Which project will you choose of you apply the NPV decision rule? c-1. Over what range of discount rates would you choose Project A? Note: Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16. c-2. Over what range of discount rates would you choose Project B? Note: Do not round…
- Bruin, Incorporated, has identified the following two mutually exclusive projects: Year Cash Flow (A) 0 -$ 54,000 1 30,000 2 24,000 18,000 12,800 3 4 Cash Flow (B) -$ 54,000 17,600 21,600 26,000 25,600 a-1. What is the IRR for each of these projects? Note: Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16. a-2. If you apply the IRR decision rule, which project should the company accept? b-1. Assume the required return is 14 percent. What is the NPV for each of these projects? Note: Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16. b-2. Which project will you choose of you apply the NPV decision rule? c-1. Over what range of discount rates would you choose Project A? Note: Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16. c-2. Over what range of discount rates would you choose Project B? Note: Do not round…Piercy, LLC, has identified the following two mutually exclusive projects: Year Cash Flow (A) Cash Flow (B) 0 −$ 66,000 −$ 66,000 1 42,000 28,400 2 36,000 32,400 3 24,000 38,000 4 15,200 24,400 a-1. What is the IRR for each of these projects? (Do not round intermediate calculations and enter your answers as a percent rounded to 2 decimal places, e.g., 32.16.) a-2. If you apply the IRR decision rule, which project should the company accept? b-1. Assume the required return is 12 percent. What is the NPV for each of these projects? (Do not round intermediate calculations and round your answers to 2 decimal places, e.g., 32.16.) b-2. Which project will you choose of you apply the NPV decision rule? c-1. Over what range of discount rates would you choose Project A? (Do not round intermediate calculations and enter your answer as a percent rounded to 2 decimal places, e.g., 32.16.) c-2. Over…You are planning to invest in three mutually exclusive investment projects, A, B and C, which have the following after-tax cash flows: Cash Flow, per year ($) Investment 0 1 2 3 4 Thereafter A (12,000) 5,000 5,000 5,000 5,000 50 B (12,000) 0 0 0 20,000 50 C (12,000) 5,000 5,000 11,000 11,000 50 Assume that your required rate of return is 6.5 percent: Apply the present-value technique to assess the acceptability of each investment.