↑ Up, Up, and Away is a producer of kites and wind socks. Relevant data on the bottleneck operation in the shop for the upcoming fiscal year are given in the following table: Wind Socks 12,000 units/year 60 units 1.0 hour/unit 4.0 hours/lot Item Demand forecast Lot size Standard processing time Standard setup time Kites 30,000 units/year 20 units 0.3 hour/unit 3.0 hours/lot The shop works two shifts per day, 8 hours per shift, 210 days per year. Currently, the company operates four machines, and desires a 25 percent capacity cushion. How many machines should be purchased to meet the upcoming year's demand without resorting to any short-term capacity solutions? The number of additional machines required is. (Enter your response rounded up to the next whole number.)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question
K
Up, Up, and Away is a producer of kites and wind socks. Relevant data on the bottleneck operation in the shop for the upcoming fiscal year are given in the following table:
Item
Demand forecast
Lot size
Standard processing time
Standard setup time
Kites
30,000 units/year
20 units
0.3 hour/unit
3.0 hours/lot
Wind Socks
12,000 units/year
60 units
1.0 hour/unit
4.0 hours/lot
The shop works two shifts per day, 8 hours per shift, 210 days per year. Currently, the company operates four machines, and desires a 25 percent capacity cushion. How many machines should be
purchased to meet the upcoming year's demand without resorting to any short-term capacity solutions?
The number of additional machines required is. (Enter your response rounded up to the next whole number.)
Transcribed Image Text:K Up, Up, and Away is a producer of kites and wind socks. Relevant data on the bottleneck operation in the shop for the upcoming fiscal year are given in the following table: Item Demand forecast Lot size Standard processing time Standard setup time Kites 30,000 units/year 20 units 0.3 hour/unit 3.0 hours/lot Wind Socks 12,000 units/year 60 units 1.0 hour/unit 4.0 hours/lot The shop works two shifts per day, 8 hours per shift, 210 days per year. Currently, the company operates four machines, and desires a 25 percent capacity cushion. How many machines should be purchased to meet the upcoming year's demand without resorting to any short-term capacity solutions? The number of additional machines required is. (Enter your response rounded up to the next whole number.)
Expert Solution
Step 1

Process capacity is the production capacity of workers or machines which states the number of hours invested to produce a finished product in an organisation.

trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,