Using the data to determine the EOQ. Only for non-integer results, round your answer UP to the nearest integer. For example, if your answer is 5.05, type 6; if your answer is 5, type 5. The formula is as follows. 2DCO Economic Order Quantity (EOQ), Q* = Cn

Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Don R. Hansen, Maryanne M. Mowen
Chapter20: Inventory Management: Economic Order Quantity, Jit, And The Theory Of Constraints
Section: Chapter Questions
Problem 7E: Ottis, Inc., uses 640,000 plastic housing units each year in its production of paper shredders. The...
icon
Related questions
Question
100%
Net Steels is a steel manufacturing company. It currently orders 180 metric tons of raw material per order. It was
observed that the company often faces stockout. To tackle this issue, the company incorporated a fixed-quantity system
(FQS) and collected the following data.
Demand
Order Cost
Item Cost
12000 metric tons per year
$16000 per order
$35000 per year
20 percent per year
Inventory-Holding Cost
Using the data to determine the EOQ. Only for non-integer results, round your answer UP to the nearest integer. For
example, if your answer is 5.05, type 6; if your answer is 5, type 5.
The formula is as follows.
2DCO
Economic Order Quantity (EOQ), Q* =
Ch
Reorder point, r = demand rate x lead time = d L
Your Answer:
Answer
Transcribed Image Text:Net Steels is a steel manufacturing company. It currently orders 180 metric tons of raw material per order. It was observed that the company often faces stockout. To tackle this issue, the company incorporated a fixed-quantity system (FQS) and collected the following data. Demand Order Cost Item Cost 12000 metric tons per year $16000 per order $35000 per year 20 percent per year Inventory-Holding Cost Using the data to determine the EOQ. Only for non-integer results, round your answer UP to the nearest integer. For example, if your answer is 5.05, type 6; if your answer is 5, type 5. The formula is as follows. 2DCO Economic Order Quantity (EOQ), Q* = Ch Reorder point, r = demand rate x lead time = d L Your Answer: Answer
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Information system controls
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Principles of Cost Accounting
Principles of Cost Accounting
Accounting
ISBN:
9781305087408
Author:
Edward J. Vanderbeck, Maria R. Mitchell
Publisher:
Cengage Learning