preview

Doctor

Decent Essays

PMP® Formula Pocket Guide
Print it - Fold it - Study wherever you go.

Earned Value
CV = EV - AC CPI = EV / AC SV = EV - PV SPI = EV / PV EAC ‘no variances’ = BAC / CPI EAC ‘fundamentally flawed’ = AC + ETC EAC ‘atypical’ = AC + BAC - EV EAC ‘typical’ = AC + ((BAC - EV) / CPI) ETC = EAC - AC ETC ‘atypical’ = BAC - EV ETC ‘typical’ = (BAC - EV) / CPI ETC ‘flawed’ = new estimate Percent Complete = EV / BAC * 100 VAC = BAC - EAC EV = % complete * BAC

Mathematical Basics
Average (Mean) = Sum of all members divided by the number of items. Median = Arrange values from lowest value to highest. Pick the middle one. If there is an even number of values, calculate the mean of the two middle values. Mode = Find the value in a data set that …show more content…

Payback Period = Add up the projected cash inflow minus expenses until you reach the initial investment. BCR = Benefit / Cost CBR = Cost / Benefit Opportunity Cost = The value of the project not chosen.

Communications
Communication Channels = n * (n-1) / 2

Probability
EMV = Probability * Impact in currency

Procurement
PTA = ((Ceiling Price - Target Price) / Buyer's Share Ratio) + Target Cost

Depreciation
Straight-line Depreciation: Depr. Expense = Asset Cost / Useful Life Depr. Rate = 100% / Useful Life Double Declining Balance Method: Depr. Rate = 2 * (100% / Useful Life) Depr. Expense = Depreciation Rate * Book Value at Beginning of Year Book Value = Book Value at beginning of year - Depreciation Expense Sum-of-Years' Digits Method: Sum of digits = Useful Life + (Useful Life - 1) + (Useful Life - 2) + etc. Depr. rate = fraction of years left and sum of the digits (i.e. 4/15th)

AC BAC BCR CBR CPI CV DUR EAC EF EMV ES ETC EV FV IRR LF LS NPV PERT PTA PV PV ROI SPI SV VAC σ ^

Actual Cost Budget at Completion Benefit Cost Ratio Cost Benefit Ratio Cost Performance Index Cost Variance Duration Estimate at Completion Early Finish Expected Monetary Value Early Start Estimate to Complete Earned Value Future Value Internal Rate of Return Late Finish Late Start Net Present Value Program Evaluation and Review Technique Point of Total Assumption Planned Value Present Value Return on Investment Schedule Performance Index Schedule Variance Variance at

Get Access