Psy 270 Week 6 Case Analysis

Satisfactory Essays

The earned value analysis has led to see the project will control the actual budget, which is $18,000. The actual cost at the period 4 totaled to be $7,050, and total of earned value at period 4 is $7,750. The estimate at completion for typical is $22,550. These variances show that this project will exceed the original budget of $18,000, so we are still exceeding the project’s original budgets. The SPI is less than a value of 1, which means that the project will also over schedule and activity plans. The requests immediate actions from the third-party company.