247. To determine a subcontractor's probable financial stability, which of the following would be the most relevant area for inquiry? A. Bonding rate and capacity. B. Cost of general liability insurance. C. Experience of their project managers. D. History of completed projects. 248. The most effective procurement system includes which of the following? A. Submittal log maintained weekly. B. Management system which tracks the number of submittals still outstanding. C. Log system which tracks how long the design team takes to review each submittal. D. Log which maintains fabrication, estimated and actual delivery, and installation dates. 249. Which stage of the management process has the greatest impact on the success of a project? A. Staffing. B. Planning. C. Monitoring. D. Implementing.

Fundamentals Of Construction Estimating
4th Edition
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Pratt, David J.
Chapter8: Pricing Generally
Section: Chapter Questions
Problem 5RQ
icon
Related questions
Question
247. To determine a subcontractor's probable financial stability, which of the following would be the most relevant
area for inquiry?
A. Bonding rate and capacity.
B. Cost of general liability insurance.
C. Experience of their project managers.
D. History of completed projects.
248. The most effective procurement system includes which of the following?
A. Submittal log maintained weekly.
B. Management system which tracks the number of submittals still outstanding.
C. Log system which tracks how long the design team takes to review each submittal.
D. Log which maintains fabrication, estimated and actual delivery, and installation dates.
249. Which stage of the management process has the greatest impact on the success of a project?
A. Staffing.
B. Planning.
C. Monitoring.
D. Implementing.
Transcribed Image Text:247. To determine a subcontractor's probable financial stability, which of the following would be the most relevant area for inquiry? A. Bonding rate and capacity. B. Cost of general liability insurance. C. Experience of their project managers. D. History of completed projects. 248. The most effective procurement system includes which of the following? A. Submittal log maintained weekly. B. Management system which tracks the number of submittals still outstanding. C. Log system which tracks how long the design team takes to review each submittal. D. Log which maintains fabrication, estimated and actual delivery, and installation dates. 249. Which stage of the management process has the greatest impact on the success of a project? A. Staffing. B. Planning. C. Monitoring. D. Implementing.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps

Blurred answer
Knowledge Booster
Bid package
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Fundamentals Of Construction Estimating
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:
9781337399395
Author:
Pratt, David J.
Publisher:
Cengage,