[6 marks] Carefully draw an AON network diagram for the project, and perform both the forward and backward passes in a PERT critical path analysis.
Q: scenarios of a project activities (tables given below) and their required times to be completed in…
A: In this question is about the critical path where we have to make a network diagram and have to show…
Q: A project for improving a billing process has the following precedence relationships and activity…
A:
Q: . Draw a precedence diagram using AOA. b. Find the critical path. c. Determine the expected length…
A: Below is the solution:-
Q: Consider the following information for a project to add a drive-through window at Crestview Bank.a.…
A:
Q: a. Construct a CPM network for the design project. b. Compute the EF, LF, and slack for each…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: SESSION 2– Individual exercise (for marks) Given the following activity precedence table, please…
A: The question is related to Critical Path Analysis. The details are given.
Q: 1. Draw the network diagram. 2. Calculate the expected duration and variance of each activity. 3.…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: a. Construct the project network b. Determine the critical path C Find the completion time of the…
A: Below is the solution:-
Q: A) Draw the Gantt Chart B) Draw the Network Diagram C) Identify and draw the critical path using the…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: a. Draw the project network diagram. b. What completion date would you recommend?
A: Below is the solution:-
Q: 1. Organize the infomation above in an activity precedence table showing the activity, precedent and…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: 5. Calculate the slack time of the non-critical path activities 6. Identify the critical path…
A: Formula:
Q: Consider following data. Draw activity on arc (AOA) network diagram. Find out critical path,…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: ID Immediate Time (weeks) Predecessor A 6 B. 4 3. D. A, B, C 7 4. F D 2 H. ID Cost by week (in…
A:
Q: Based on the set of activities below Description Task Must Follow Time (Weeks) Draw data flow A None…
A: PERT Diagram: Kindly find the PERT diagram below: Calculation methods: Assume 0 for start…
Q: A project consists of ten activities as detailed below. Draw an A-O-A diagram representation for the…
A: A-O-A Network Diagram :
Q: Q:2 Draw AOA and AON network diagrams and gantt chart for the project, calculate TE for each…
A: Below is the solution:-
Q: a. Calculate ALL the missing (?) data points. b. Draw the PERT network from the given data. c.…
A: NOTE: We are allowed to do the first three sub-parts only. PERT is a project management tool used…
Q: 1. Construct the activity-on-node network. 2. Identify the critical path. 3. Compute the duration of…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Table 1 Activities Immediate Predecessors Time (In Days) A 9. -- В A C A 9. B,C 6. E В, С 7 F 10 G E…
A:
Q: a)Construct AON diagram for the following data. b) Identify path, path duration and critical path c)…
A: Below is the solution:-
Q: a) Construct a Gantt chart using MS Project 2016 b) Assuming the default 5-day workweek, calculate…
A: This question is related to the topic of Project Management and this topic falls under the…
Q: (a) Draw the network diagram. Please add drawing here (photo may be added if hand drawn) (b) Using…
A: A project network is the graphical representation of project activities and their duration to…
Q: accompanying Table 1 shows the activities, times and sequences required for the project planning and…
A: the critical path is a step by step technique to identify the critical activities in the project.…
Q: a. Develop a network diagram for the project using AON convention. b. Determine the project…
A: Here, in the question, we have the activity id, a description of each activity, immediate…
Q: i. Calculate the expected time for each activity ii. Draw a Gantt Chart from the same information…
A: As per Bartleby guidelines we can only solve first 3 sub par Below is the solution:-
Q: Build a PERT Analysis for a 3-month project with 6 activities (A to F) and 5 nodes
A: The PERT Method (or Program Evaluation and Review Approach) is a standard network analysis…
Q: The following information has been gathered for a project to install a new machine lathe at Diamond…
A: a.
Q: a. Draw a network diagram and determine the expected project completion time b. What is the…
A: Below is the solution:-
Q: 5. Construct an activity-on-arrow precedence diagram for each of the following cases. Note that each…
A: The project network is the visual representation of the project activities and their durations to…
Q: The activities related to a project with their immediate predecessors are given as follows: Activity…
A: Given data is
Q: (a) Explained the reason of applying probabilistic time estimate (PERT) instead of using CPM in…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: 7. The project information for the custom order project of the Air Control Comp presented here. Draw…
A:
Q: a. Draw a precedence diagram using AOA , AON and Gantt chart. b. Find the critical path using CPM.…
A: Below is the solution:-
Q: Task time estimates for a production line setup project at XYZ Company are as follows; Activity Time…
A: We are authorized to answer three subparts at a time since you have not mentioned which part you are…
Q: The following Table 1 contains a list of activities, with precedence requirements and crash costs.…
A: The network diagram is shown below
Q: Task bme estimates for the modification of an assembly line at Jim Goodale's Carbondale, linois,…
A: A Gantt chart usually practiced in project management, is the most widespread and helpful means of…
Q: 2. Consider the data given in the following table and give what is asked. Immediate Normal Time…
A: Find the Given details below: Activity Predecessor Original duration (NT) (Days) Original cost…
Q: PERT-CPM 1. Consider a project involving the following activities and precedence relationship. The…
A:
Q: Given the activities whose sequence is describedby the following table, draw the appropriate…
A: Draw the path
Q: Crash the project until no more crash can be performed How much it would cost The new critical…
A: Proect crashing is one of the techniques used in the calculation of the duration of the critical…
Q: Immediate Activity Predecessor Time (days) 8 в 20 33 18 D E 20 F B B.C 10 H D EF G, H, I 4 (End) a)…
A: A network diagram is a visual representation of a project which helps to identify the project…
Q: Questions 1. Organize the information above in an activity precedence table showing the activity,…
A: Answer of all pats are below:-
Q: Based on the Table 1, using Critical Path Method (CPM) diagram, determine the ES, EF, LS & LF,…
A:
Q: 1. What is the expected (estimated) time for each activity? 2. Based on the calculation of estimated…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: • Draw the Network diagram. • Calculate expected time and variance for each activity. • Find the…
A: Let: a= OPTIMISTIC TIME b= PESSIMISTIC TIME m= MOST LIKELY TIME Te = EXPECTED TIME = (a+4m+b)/6…
Q: Draw the project network diagram. 1. What is the total time required to complete the project if no…
A: Network analysis (NA) could be a set of integrated techniques to depict relations among actors and…
Q: A senior MIS design class project team has developed the following schedule of activities for their…
A: The project network diagram helps in finding the duration of the project. It can also help in…
Q: a. Construct the project network b. Determine the critical path c. Find the completion time of the…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Step by step
Solved in 3 steps with 2 images
- c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 2 decimal places.) Project completion time d. What is the probability of completing this project within 16 days? (Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "2" value to 2 decimal places and final answer to 4 decimal places.) Probability 10 00 days 09994States) B E- Text Predictions: On Activity A I U 2. Given below are additional details for the Evergreen Company's construction project, i.e. three time estimates. B C D ALL E F Optimistic 0.5 ARDCCDGEe Normal 2.5 1 0.9 0.5 Most Likely 1 2 3 2 1 AaBb CcDdEe No Spacing 1 AaBbCcL AaBbCcDd. Heading 1 Heading 2 Pessimistic 2 2.5 3.5 3 1.1 1.5 a) Calculate the expected completion times and completion variances for each activity. b) What are the expected days to completion now for Evergreen? c) Compute the variance and standard deviation of the Evergreen project's completion time. d) What is the probability that the Evergreen Company's project can be completed in 6.5 days? e) What would be Evergreen Company's completion days if we needed a 95% confidence level? f) Which noncritical activities should Evergreen Company monitor closely? Why? Focus EUsing PERT, Adam Munson was a ble to determinethat the expected project completion time for the construction ofa pleasure yacht is 21 months, and the project va riance is 4.a) What is the probability that the project will be completed in17 months?b) What is the probability that the project will be completed in20 months?c) What is the probability that the project will be completed in23 months?d) What is the probability that the project will be completed in25 months?e) What is the due date that yields a 95% chance of completion?
- The following precedence diagram reflects three time estimates for each activity. Determine: Use Table B1 and Table B2. 9-10-12 3 8 5-7-10 8-10-14 11-12-13 6 11 14-18-26 10.5-13-15.5 10 8-8-8 1 5-6-7 2 4 13-13-13 7 7-10-12 a. The expected completion time for each path and its variance. (Round intermediate calculations to 4 decimal places and final answers to 2 decimal places.) Path Mean Var. Std. Dev. 1-2-3-8-11 37.33 1-2-4-6-11 43.00 5.11 1-2-4-7-11 0.81 1-2-5-9-10-11 46.83 1.25 9-9-9 10-11-12 10-12-14Management Firm is a consulting company that specializes in the development of decision support systems. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Report generation 2 8 12 B Web scraping 4 9 11 C Testing A, B 1 1 1 (b) Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.)AABCDE Activity J К Predecessor None PZABUD FGHL-KL EOFICI LA C H с H J.I,K Draft PDS Identify team Kickoff team meeting Source previous rocket Identify & order missing or new materials/parts Assembly Simulation Alpha Test Beta Test Training of key people Buy food to bring Launch DITONT Duration (wks) 1 1 0 2 4 8722860 1. Show the Critical Path. Give reasons for your answer. 2. If you needed to shorten the duration of the project, which activity or activities would you shorten and why?
- The following represents a project that should be scheduled using CPM: ACTIVITY ABCDEFGH А с IMMEDIATE PREDECESSORS IAABUDR C,D D,E F,G TIMES (DAYS) b a 1 1 3 - NTTTTE 1 1 1 1 2 m 5 WaNNASNU 2 5 4 2 2 6 3 ∞∞NWO3770 9 10 12 8I want answer with explanation... I'll upvote you... Only typed answer I want... The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Activity optimistic time most likely time pessimistic time Activity Predecessor A 1 4 7 -- B 2 6 7 -- C 3 3 6 B D 6 13 14 A E 3 6 12 A, C F 6 8 16 B G 1 5 6 E, F Table 1 Reference: Ref 1 Using Table 1, the probability that the project could be completed in 23 weeks or less is approximately A. 0.94 B. 0.87 C. 0.91 D. 0.89Management Firm is a consulting company that specializes in the development of decision support systems. Time (Weeks) Activity Description ImmediatePredecessor Optimistic Most Probable Pessimistic A Report generation 2 8 12 B Web scraping 4 9 11 C Testing A, B 1 1 1 (A) Based solely on the critical path, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.) (b) Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (Round your answer to four decimal places.)
- empt.php/attempt 1839268cmki 73847 Management Sec-1 with Ja Quizzes/ Quiz 2 Duration of Dummy activity is always constant Select one: O True O FalseO O D 40 4 22:31 photo_2021-02-2... O By using Bar chart planning method, find the following: - Total duration for the project activities shown below - The project completion date (assume the start date is 1/3/2012 Activity A В CDEF GHIJ Duration 8 28 4 6. 4 5 6 (days) Following C,DEFGH Activity * If the project shown above had a delay of (4 days after (13working days), what would its new delivery date be? 7. 5,A project consists of five activities as shown in the following table. Activity Floor sanding Floor buffing Paint mixing Wall painting Ceiling painting Optimistic Time (hr) Most Probable Time (hr) 4 4 0.5 2 3 5 5 Сл 1 3 7.5 Pessimistic Time (hr) 6 6 1.5 10 9 Naturally, the paint mixing precedes the painting activities. Also, both ceiling painting and floor sanding must be done prior to floor buffing. (a) Construct the PERT/CPM network for this problem.