__________2a) What steps comprise the “critical path”? __________2b) What is the minimum completion time?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

Given the following table of activities and times, determine the critical path and duration.
Activity Description Predecessor Duration (weeks)
A Task A --- 2
B Task B A 4
C Task C B 5
D Task D A 1
E Task E B, D 3
F Task F C 2
G Task G E 5
H Task H F, G 1
__________2a) What steps comprise the “critical path”?
__________2b) What is the minimum completion time? 

2. Given the following table of activities and times, determine the critical path and duration.
Activity Description
Predecessor
Duration (weeks)
A
Task A
2
---
B
Task B
A
4
Task C
в
5
D
Task D
A
1
E
Task E
В, D
3
Task F
2
G
Task G
E
5
H
Task H
F, G
1
2a) What steps comprise the “critical path"?
2b) What is the minimum completion time?
Transcribed Image Text:2. Given the following table of activities and times, determine the critical path and duration. Activity Description Predecessor Duration (weeks) A Task A 2 --- B Task B A 4 Task C в 5 D Task D A 1 E Task E В, D 3 Task F 2 G Task G E 5 H Task H F, G 1 2a) What steps comprise the “critical path"? 2b) What is the minimum completion time?
Expert Solution
Step 1

A project network is a graphical network that shows the duration of project activities and their dependencies.

trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.