Clients are served in a process with two resources. A worker in the first resource serves 2.4 clients per hour and a worker in the second resource serves 1.3 clients per hour. The first resource has 1 worker and the second resource has 2 workers. Demand occurs at the rate 3.2 clients per hour. Instruction: Round your answer to 1 decimal place. What is the utilization (%) of the second resource? % Chairs are made in a process with two resources. The first resource has a capacity of 6 chairs per hour. The capacity of the second resource is 8.4 chairs per hour. Demand for this process is 8.4 chairs per hour. Instruction: Round your answer to three decimal places. What is the cycle time of this process (in minutes)? minutes

Oh no! Our experts couldn't answer your question.

Don't worry! We won't leave you hanging. Plus, we're giving you back one question for the inconvenience.

Submit your question and receive a step-by-step explanation from our experts in as fast as 30 minutes.
You have no more questions left.
Message from our expert:
Hi and thanks for your question! Unfortunately we cannot answer this particular question due to its complexity. We've credited a question back to your account. Apologies for the inconvenience.
Your Question:

please help

Clients are served in a process with two resources. A worker in the first resource serves 2.4 clients per hour and a worker in the
second resource serves 1.3 clients per hour. The first resource has 1 worker and the second resource has 2 workers. Demand occurs at
the rate 3.2 clients per hour.
Instruction: Round your answer to 1 decimal place.
What is the utilization (%) of the second resource?
%
Transcribed Image Text:Clients are served in a process with two resources. A worker in the first resource serves 2.4 clients per hour and a worker in the second resource serves 1.3 clients per hour. The first resource has 1 worker and the second resource has 2 workers. Demand occurs at the rate 3.2 clients per hour. Instruction: Round your answer to 1 decimal place. What is the utilization (%) of the second resource? %
Chairs are made in a process with two resources. The first resource has a capacity of 6 chairs per hour. The capacity of the second
resource is 8.4 chairs per hour. Demand for this process is 8.4 chairs per hour.
Instruction: Round your answer to three decimal places.
What is the cycle time of this process (in minutes)?
minutes
Transcribed Image Text:Chairs are made in a process with two resources. The first resource has a capacity of 6 chairs per hour. The capacity of the second resource is 8.4 chairs per hour. Demand for this process is 8.4 chairs per hour. Instruction: Round your answer to three decimal places. What is the cycle time of this process (in minutes)? minutes
Knowledge Booster
Business reports
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,