Michael Julius received an $18,000 payment in advance on a three-month contract to install a water purification system. By month-end the project is one-third completed. Determine the amount of revenue to be recognized in the current period.
Q: January 1, year 1, a company has capitalized software costs of $1,200,000 related to software that…
A: Amortization means the expensing out the non-tangible asset's cost over the expected benefit to be…
Q: Cullumber Landscaping began construction of a new plant on December 1, 2020. On this date, the…
A: Capitalized costs are those costs that are added to the purchase price of the non-current assets to…
Q: On January 1, Year 1, Crawford Construction Company enters into a contract with a customer to build…
A: Revenue to be recognised = Price * Percentage of completion
Q: On March 1, Imhoff Co. began construction of a small building. Payments of $800,000 were made…
A: Fixed Assets: It refers to the long-term assets having a useful life of more than a year which is,…
Q: O'Connor Company ordered a machine on January 1 at a purchase price of $95,000. On the date of…
A: Note: Since we only answer up to 3 sub-parts, we’ll answer the first 3. Please resubmit the question…
Q: You were engaged to audit the books of accounts of A. Bonifacio contractors which had a 3 year…
A: The question is related to Construction Contacts. The details are given regarding the Construction…
Q: . Allee Corp. is evaluating a revenue arrangement to determine proper revenue recognition. The…
A: According to ASC 606 Tin this case amount of variable consideration will be calculated by using -…
Q: Batman Company paid the annual fee of P30,000 for an equipment maintenance contract on July 1, the…
A: Annual Equipment Maintenance Contract is of P30,000 taken on 1-July(beginning of quarter). Expense…
Q: etermine the transaction price for the contract, assuming Headland is only able to estimate
A:
Q: In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: Requirement 4 : 2018 2019 2020 Revenue $ 2,800,000 $ 3,692,964 $…
Q: On January 1, 20x6, BUNNY, a real estate company, entered into a contract to construct a subdivision…
A: Answer - Given, Estimated total cost of contract for the 10 houses = P40M. In CY 20x6, total…
Q: 1- On November 1, 2018, Almadinah Company contracted Pfeifer Construction Co. to construct a…
A: Financial Instrument- It includes those instruments which helps the entity in collecting funds from…
Q: DAEBAK Landscaping began construction of a new plant on December 1, 2019. On this date, the company…
A: Part a:
Q: DAEBAK Landscaping began construction of a new plant on December 1, 2019. On this date, the company…
A: Treatment of Purchase of Land and Cost of Demolition Cost of Land will include purchase price of…
Q: Bramble Company is constructing a building. Construction began on February 1 and was completed on…
A: As per the IAS 23, Borrowing cost, the general borrowing used for acquisition or construction of…
Q: The company purchases $2,000,000 of equipment to be used in its manufacturing plant. The company…
A: Real accounts include Assets, liabilities and owner's equity. For real accounts, the accounting rule…
Q: On January 1, 20x6, Bad, a real estate company, entered into a contract to construct a subdivision…
A: Current asset = revenue for year except revaluation profit on land
Q: An environmental soil cleaning company received a contract to remove BTEX contamination from an oil…
A: Service charge refers to the fee collected by the person who provides the services. Service charges…
Q: On January 1, 20x6, BUNNY, a real estate company, entered into a contract to construct a subdivision…
A: Construction accounting requires a special revenue recognition rules for contract in procee.in this…
Q: Explain how you would decide whether to record each of the following expenditures as an asset or an…
A: Assets: Assets are those items that provide value for money and future economic benefit for an…
Q: Bonita Company is constructing a building. Construction began on February 1 and was completed on…
A: A weighted average interest rate is an average that is adjusted to reflect the contribution of…
Q: On January 1, 20x6, BUNNY, a real estate company, entered into a contract to construct a subdivision…
A: Under contract costing, a contract is made between the parties on some specific project.in generally…
Q: Shamrock Company is constructing a building. Construction began on February 1 and was completed on…
A: Weighted average Interest Rate is calculated by aggregate of all interest payments in period divided…
Q: Gidi professional institute is constructing a tuition center at Aboabo that will take about 18…
A: The borrowing cost to acquire or construct a long-term asset referred to as capitalization of…
Q: On April 1st, Ma Construction entered into a contract of one-month duration to build a barn for…
A: Discounts, credits, rebates, performance bonuses, penalties, sales returns, refunds, price…
Q: On January 1, 2021, Gemini Company contracted with a contractor to construct a building for…
A: Note: Since we only answer up to 3 sub-parts, we’ll answer the first 3. Please resubmit the question…
Q: On April 1, Paine Co. began construction of a small building. Payments of P120,000 were made monthly…
A:
Q: Required: 1. The amount included as current asset in the financial statements of BUNNY related to…
A: The Current Assets are those assets from which the business is expected to derive economic benefits…
Q: On January 1, 20x6, Bad, a real estate company, entered into a contract to construct a subdivision…
A: In the case of a contract which continues for a period greater than a year, revenue is booked as per…
Q: On January 1, 2018 The Village of Port Jefferson engaged to Frog Construction company to construct a…
A: Answer A)
Q: In 2018, the Laguna Inc entered into a contract to construct a road for 5th Avenue for $14,000,000.…
A:
Q: On January 1, 20x6, Bad, a real estate company, entered into a contract to construct a subdivision…
A: Revenue = current asset
Q: On January 1, 20x6, BUNNY, a real estate company, entered into a contract to construct a subdivision…
A: While preparing the income statement all the expenditures are deducted from the revenue generated so…
Q: On January 1, 20x6, BUNNY, a real estate company, entered into a contract to construct a subdivision…
A: Answer- Working Note : Computation of Revenue to be Recognized - Particulars Working Amount P…
Q: On January 1, 20x6, BUNNY, a real estate company, entered into a contract to construct a subdivision…
A: Current assets refer to any form of asset that is monetary beneficial for an individual or an entity…
Q: Since 1970, Super Rise, Inc., has provided maintenance services for elevators. On January 1, 2018,…
A: Accrued Income: Fixed payment of $80,000 received for the project undertaken is treated as Accrued…
Q: On March 1, Wenger Co. began construction of a small building. Payments of$120,000 were made monthly…
A: In determining the amount of interest cost capitalization, the weighted-average accumulated…
Q: Dominion construction is awarded a contract to build a commercial building. The contract price is…
A: Under the cash method, revenue and expenses are recognized when a construction firm actually…
Q: Cullumber Landscaping began construction of a new plant on December 1, 2020. On this date, the…
A: Solution: Capitalizing of Land and Building cost: Land is generally considered to have an unlimited…
Q: Ayayai Company is constructing a building. Construction began on February 1 and was completed on…
A: Expenditure on March 1 = $3,600,000 Expenditure on June 1 = $4,000,000 Expenditure on December 31 =…
Q: A small industrial contractor purchased a warehouse building for storing equipment and materials…
A: The question is based on the concept of loan amortization of cost of building. The loan will be paid…
Q: On March 1, Morgan Co. began construction of a small building. Payments of $120,000 were made…
A: Solution : The weighted average accumulated expenditure are $60,000 Explanation:
Q: Prepare the necessary entries to be made by the agency for the construction of the building
A: We will be using 2 accounts to record the payments for the contract. 'Contract Advance payment 'a/c…
Q: In September of year 1, Jašon agrééd tó à čóntrăct in which he agreed to redo the floors in an…
A: Which amount Should Jason report as Income from this job in Year 1 and Year 2 ? Ans. Income for Year…
Q: On January 1, 20x6, BUNNY, a real estate company, entered into a contract to construct a subdivision…
A: Under the contract costing, the contractor is required to complete the assigned project within the…
Q: and it has acquired and, when construction is complete, to deliver the finished houses to their…
A: As per the fundamental accounting principle a revenue should be recognised only when it is earned.…
Q: Blossom Company is constructing a building. Construction began on February 1 and was completed on…
A: Borrowing cost refers to the finance cost in the form of interest and other costs on the funds…
Q: Champion Contractors completed the following transactions involving equipment. Year 1 January 1…
A: Annual Depreciation (straight line method) = (Cost of the assets - Residual value) / Expected life…
Q: On January 1, 20x6, Bad, a real estate company, entered into a contract to construct a subdivision…
A: Revenue to be recorded = contract Revenue + revaluation profit
The degree of Completion is to be calculated for determining the amount of revenue to be recognised.
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- 1. A contractor is constructing a project for which he will be paid in one lump sum upon satisfactory completion of the project. The contractor needs cash to finance the construction and opens a line of credit at their bank (the loan would be repaid at the end of the project). The construction project is expected to last 16 months, and the contractor expects to borrow $100,000 at the beginning of the first month, and at the end of each of the first six months, making a total borrowing of $700,000. The contractor then needs to borrow $250,000 per month at the end of month 7 through 16, for an additional $2,500,000. The owner agrees to pay the contractor the lump sum payment for the project at EOM 20, at which time the contractor will repay the bank. Interest on the contractors outstanding loan balance is 1.5% per month for the first 10 months and then 2% per month until EOM 20. Given this scenario, please answer the following questions. a. What is the minimum contract price for this…Consultant Inc. is a firm of consulting engineers, newly established to advise on a large project taking three years to complete. Their fee for this work is a percentage of the total project costs, payable on completion of the project. In the interim, advances on the final fee are made at six-monthly intervals. The total project costs will not be known until the project is completed. The following advances were received by Consultant Inc. during the three-year period: Year ended 31 December 20x0 K25, 000 Year ended 31 December 20x1 K30, 000 Year ended 31 December 20x2 K30, 000 When the total costs were computed during the year ended 31 December 20x0, it was found that a further sum of K50, 000 was due to Consultant Inc. REQUIRED; Explain how Consultant Inc. would show the payments made during the periods covered by the project. Justify your explanation…On January 1, 2018 The Village of Port Jefferson engaged to Frog Construction company to construct amunicipal office complex. The three-year a to receive 10 million in cash payments from the city in threeinstallments: 25% when the project was 30% complete; 25% when the project was 60% complete; and50%when the project was fully complete. The contract required that Frog's completion estimates be certifiedby an independent consultant before payments were made.During the first year of the contract, Frog completed 30% of the contract and incurred costs of 2,490,000.During the second year, the project was certified as being 60% complete and Frog incurred costs of3,100,000.During the third year, Frog completed the project and incurred costs of 3,110,000.Assuming Frog had no other revenues or expenses, determine the profit on construction for 2018, 2019,and 2020 under the following methods: A. Percentage Calculation B. Completed Contract
- Captain Construction Company is engaged in a road construction contract to build a highway over a three-year period. Captain will receive $22,000,000 for building five miles of highway Captain estimates that it will incur $20,000,000 of costs before the contract is completed. As of the end of the first year Captain incurred $5,000,000 of costs allocated to the contract Read the requirements. Requirement a. How much income from the contract must Captain report during the first year? (Do not round interim calculations. Only round the amount you input in the cell to the nearest dollar Enter a loss with a minus sign or parentheses.) Year 1 Revenue Costs Income (loss)An environmental soil cleaning company received a contract to remove BTEX contamination from an oil company tank farm site. The contract required the soil cleaning company to provide quarterly invoices for materials and services provided. If the material costs were $140,000 per quarter and the service charges were calculated as an additional 20% of the material costs, what is the present worth of the contract through the 3-year treatment period at an interest rate of 1% per month?In 2018, the Laguna Inc entered into a contract to construct a road for 5th Avenue for $14,000,000. The road was completed in 2018. Information related to the contract is as follows: Laguna uses the percentage-of-completion method of accounting for long-term construction contracts. Required: Calculate the amount of gross profit to be recognized in each of the three years. Prepare all necessary journal entries for each of the years (credit various accounts for construction costs incurred). Prepare a partial balance sheet for 2016 and 2017 showing any items related to the contract.
- Marin Construction Inc. agrees to construct a boat dock at the Smooth Sailing Marina for $32,400. In addition, under the terms of the contract, Smooth Sailing will pay Marin a performance bonus of up to $12,000 based on the timing of completion. The performance bonus will be paid fully if construction is completed by the agreed-upon date. The performance bonus decreases by $2,400 per week for every week beyond the agreed-upon completion date. Marin has constructed a number of boat docks under similar agreements. Marin’s management estimates, that it has a 60% probability of completing the project on time, a 20% probability of completing the project one week late, and a 20% probability of completing the project two weeks late. Management does not believe the project will be more than two weeks late.Determine the transaction price that Marin should compute for this agreement.On April 1st, Ma Construction entered into a contract of one-month duration to build a barn for Valley Properties. Ma is guaranteed to receive a base fee of $5,000 for its services in addition to a bonus depending on when the project is completed. Valley Properties created incentives for Ma to finish the barn as soon as they can without jeopardizing the structural integrity of the barn. Valley offered to pay an additional 30% of the base fee if the project finished 2 weeks early and 10% if the project finished a week early. The probability of finishing 2 weeks early is 30% and the probability of finishing a week early is 60%.What is the expected transaction price with variable consideration estimated as the most likely amount? Group of answer choices $5,000 $5,750 $5,500 $4,750In 2018, the Laguna Inc entered into a contract to construct a road for 5th Avenue for $14,000,000. The road was completed in 2018. Information related to the contract is as follows: Laguna uses the completed contract method of accounting for long-term construction contracts. Calculate the amount of gross profit to be recognized in each of the three years. Prepare all necessary journal entries for each of the years (credit various accounts for construction costs incurred). Prepare a partial balance sheet for 2016 and 2017 showing any items related to the contract.
- Johnson Inc. enters into a $300,000 contract for the purchase of customized equipment with Builder Inc. The construction of the equipment is expected to take two years. Johnson Inc. owns the work in process during the two-year period but will not take possession of the equipment until completed. The contractor will bill Johnson monthly for performance completed to date. After year-one, Builder Inc. incurred costs of $120,000 and expects remaining costs to be $108,000. Builder Inc. has billed Johnson $150,000 in total for the year. Johnson has paid $135,000 to Builder Inc. Determine the amount of revenue and expenses that Builder Inc. should recognize in the first year of the contract.Johnson Inc. enters into a $300,000 contract for the purchase of customized equipment with Builder Inc. The construction of the equipment is expected to take two years. Johnson Inc. owns the work in process during the two-year period but will not take possession of the equipment until completed. The contractor will bill Johnson monthly for performance completed to date. After year-one, Builder Inc. incurred costs of $120,000 and expects remaining costs to be $108,000. Builder Inc. has billed Johnson $150,000 in total for the year. Johnson has paid $135,000 to Builder Inc. Determine the amount of revenue and expenses that Builder Inc. should recognize in the first year of the contract. a. Revenue Expenses $157,895 $120,000 b. Revenue Expenses $150,000 $114,000 c. Revenue Expenses $78,947 $120,000 d. Revenue Expenses $0 $0 e. Revenue Expenses $150,000 $120,000On September 30, 2019, STONE REACH Co., Inc. was awarded the contract to build a 1,000 room hotel for P24,000,000. Among others, the parties agreed to the following:1.Ten percent mobilization fee (deductible from "final billing") payable within ten days from the signing of the contract.2.Retention of ten per cent on all billings (to be paid with the final billing, upon completion and acceptance of the project); and 3.Progress billings are to be paid within 2 weeks upon acceptance. By the end of 2019, the company had presented one progress billing, corresponding to 10% completion, which was evaluated and accepted by the client on December 29, 2019 for payment in January of the next year. In 2019, assuming use of the percentage-of-completion method of accounting STONE REACH Co., Inc. received a total fee of