Mike is the manager of the DEF project. This project will cost Mike’s organisation $90,000 per day if it runs over schedule. With four months to completion, Mike realises the project is behind schedule. He decides to change the relationship between some work packages so that they begin in tandem rather than sequentially. This is an example of___________. Group of answer choices Crashing Expert judgment Fast tracking Cost-benefit analysis

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
Question

Mike is the manager of the DEF project. This project will cost Mike’s organisation $90,000 per day if it runs over schedule. With four months to completion, Mike realises the project is behind schedule. He decides to change the relationship between some work packages so that they begin in tandem rather than sequentially. This is an example of___________.

Group of answer choices
Crashing
Expert judgment
Fast tracking
Cost-benefit analysis
Expert Solution
steps

Step by step

Solved in 4 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Understanding Management (MindTap Course List)
Understanding Management (MindTap Course List)
Management
ISBN:
9781305502215
Author:
Richard L. Daft, Dorothy Marcic
Publisher:
Cengage Learning