The desired daily output for an assembly line is 300 units. This assembly line will operate 375 minutes per day. The following table contains information on this product's task times and precedence relationships: TASK TIME (SECONDS) 30 35 30 IMMEDIATE PREDECESSOR - A A B IT in in 333164 TASK А В с ABCDEECE 35 15 65 F G 40 H 25 E-F D-G b. What is the required workstation cycle time to meet the desired output rate? Workstation cycle time seconds per unit

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question
The desired daily output for an assembly line is 300 units. This assembly line will operate 375 minutes per day. The following table
contains information on this product's task times and precedence relationships:
TASK
TASK TIME
(SECONDS)
ADCOACH
А
30
B
35
с
30
35
E
15
F
65
G
40
Н
25
IMMEDIATE
PREDECESSOR
-
B
с
AADCC
E-F
D-G
b. What is the required workstation cycle time to meet the desired output rate?
Workstation cycle time
seconds per unit
Transcribed Image Text:The desired daily output for an assembly line is 300 units. This assembly line will operate 375 minutes per day. The following table contains information on this product's task times and precedence relationships: TASK TASK TIME (SECONDS) ADCOACH А 30 B 35 с 30 35 E 15 F 65 G 40 Н 25 IMMEDIATE PREDECESSOR - B с AADCC E-F D-G b. What is the required workstation cycle time to meet the desired output rate? Workstation cycle time seconds per unit
c. Balance this line using the largest number of following tasks. Use the longest task time as a secondary criterion.
Note: Leave no cells blank - be certain to enter "0" wherever required.
Work Station
Task
Idle Time
1
2
3
4
d. What is the efficiency of your line balance, assuming it is running at the cycle time in part b?
Note: Round your answer to 1 decimal place.
Transcribed Image Text:c. Balance this line using the largest number of following tasks. Use the longest task time as a secondary criterion. Note: Leave no cells blank - be certain to enter "0" wherever required. Work Station Task Idle Time 1 2 3 4 d. What is the efficiency of your line balance, assuming it is running at the cycle time in part b? Note: Round your answer to 1 decimal place.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 6 steps with 8 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,