Question
Chapter 4, Problem 8CQ
Summary Introduction
To explain: The way Takt time changes as the demand rate increases.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
How does the takt time change as the demand rate increases?a. The takt time increases.b. The takt time stays the same.c. The takt time decreases.d. Cannot determine from the given information.
One of the chair lifts at a ski resort unloads 1,600 skiers per hour at the top of the slope. The ride from the bottom to the top takes 19
minutes.
Instruction: Do not round your intermediate and round final answer to nearest integer.
How many skiers are riding on the lift at any given time?
skiers
4-
Which of these is the correct order of the controlling function?
a.
Setting standards, measuring actual performance, comparing, correcting deviations, finding deviations
b.
Setting standards, measuring actual performance, comparing, finding deviations, correcting deviations
c.
Setting standards, comparing, finding deviations, measuring actual performance, correcting deviations
d.
Measuring actual performance, comparing, finding deviations, setting standards correcting deviations
Chapter 4 Solutions
Operations Management
Ch. 4 - Prob. 1CQCh. 4 - Prob. 2CQCh. 4 - Prob. 3CQCh. 4 - Prob. 4CQCh. 4 - Prob. 5CQCh. 4 - Which of the following statements about takt time...Ch. 4 - Prob. 7CQCh. 4 - Prob. 8CQCh. 4 - How does the target manpower change as the demand...Ch. 4 - What happens to the target manpower if the labor...
Ch. 4 - Which of the following actions does not relate to...Ch. 4 - Prob. 12CQCh. 4 - Prob. 13CQCh. 4 - Prob. 14CQCh. 4 - Specialization typically leads to a higher average...Ch. 4 - Prob. 16CQCh. 4 - Prob. 17CQCh. 4 - Prob. 18CQCh. 4 - Prob. 1PACh. 4 - Prob. 2PACh. 4 - Prob. 3PACh. 4 - Prob. 4PACh. 4 - Prob. 5PACh. 4 - Prob. 6PACh. 4 - Prob. 1C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- A nonbottleneck worker currently has an idle time of 20 seconds per unit. Because ofthe large demand, the company improves the process by adding more capacity to thebottleneck. How does this impact the idle time of the worker?a. The idle time would decrease.b. The idle time would stay the same.c. The idle time would increase.d. Cannot determine from the given informationarrow_forwardA customer service department has the following resolution response time data: Average Response Time First contact 0.25 hr. Service scheduling 0.50 hr. Wait for service 24.00 hrs. Service 1.50 hrs. Total resolution time 26.25 hrs. What is the value-added ratio (rounded to one decimal place) in this process? a. 8.6% b. 91.4% c. 5.7% d. 28.6%arrow_forwardOutput from the Gantt chart drawn for a machining process is shown here. Determine the makespan of the process. Job Waiting Time (hr) Delivery Time (hr) 1 0 10 2 10 15 3 1 16arrow_forward
- A car manufacturer has designed a “special edition” version of its popular two-doorcoupe. This special edition has increased horsepower compared to the standard modeland a sports suspension. Which dimension of the customer utility function is particularly emphasized with the special edition coupe?a. Performanceb. Fitc. Priced. Timingarrow_forwardThink about the benefits and drawbacks of a manual task. response program (in which the customer calculates the answer) hand or mentally) a system that necessitates the use of a special computer, such as as a calculating devicearrow_forwardWe measure, monitor and improve process cycle time because: a. It is an easy measurement to make *b. Increasing cycle time helps us improve the capacity of the process and reduce costs c. Everyone understands cycle time d. Customers are interested in how long it takes to make a product e. All of the above f. None of the abovearrow_forward
- Personal observation is a technique used by management to personally observe operations in the work place Select one: O a. True O b. Falsearrow_forward8. A furniture company just completed a work analysis on the total completion time for dying process of handmade dining tables. They have concluded that on average the process takes 27 minutes. However they want to incorporate the performance of the workers and allowance time on this observed value. They think the people they observed was somehow slow, hence they want to use a performance rate of 0.93 and they also want to allow 10% (allow=0.1) of job time. Based on these parameters please calculate the normal and standard time estimates for this process.arrow_forward24 - Which of the following is the concept of wage calculated based on the result of the work done? a) Tuning Fee B) Fee by Time NS) Fee Paid by Percentage D) Lump-sum Fee TO) Premiumarrow_forward
- While designing a process, we try to ensure that unpleasant experiences such as filling forms or taking shots are located towards the beginning/middle, primarily because: O It is usually more convenient to complete such tasks early on None of the above We do not wish to end on an unpleasant note. The memory of unpleasant experiences stays much longer relative to other kinds of experiences. O The customer may refuse to do/participate in such unpleasant tasks at the end of the processarrow_forwardCompanies use job rotation as a technique to increase worker efficiency. a. True b. Falsearrow_forwardc)Time required for the fifth unit = ? enter your response here hours (round your response to the nearest whole number).arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.